Title Page
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
The person receiving the contents of this report
-
Signature
PPE & RAMS
-
Take a photo of all operatives in full PPE
-
Add media
-
I can work to the RAMS I have been issued
-
I can work with in TG20:13 and my compliance sheet
Public Segregation
-
Is the public segregated from the work area
-
Are there any work in sensitive areas i.e cash points/doorways <br>Have controls put in place<br>Out of order signs <br>Closed doors
Ladders
-
All ladders to be checked and in good condition
-
Ladder secured and of the correct length
-
Add media
SCAFFOLD BASE
-
Are all baseplates and sole boards present ?
-
Are all baseplates on a solid and even surface ?
GEOMETRY
-
Are the ledger and standard joints staggered between lifts ?
-
Are ledgers and standards horizontal and vertical ?
-
Are the transoms correctly spaced ?
PLATFORMS
-
Are scaffold boards sound and clipped
-
Are the butt joints at least 50mm and no more than 150mm ?
-
Are platforms fully boarded ?
-
Add media
BRACING
-
Are all facade bracings correct ?
-
Are all ledger bracings correct ?
-
Are all plan bracings correct ?
-
Are materials in good condition ?
-
Are check couplers in place and correct ?
-
Are the correct couplers being used ?
-
Are all couplers tightened ?
HANDRAILS + TOE BOARDS
-
Are all handrails present and gaps not exceeding 470mm ?
-
Are all handrails secured and at least 950mm above the platform ?
-
Are all toe boards in place, correctly fitted and at least 150mm high ?
-
Are Ladder gates / hatches fitted ?
-
Are access staircases sound and tied to the main structure ?
-
Are all stair treads tightened
LOADING
-
Are Materials evenly distributed and within the load class >
-
Are materials stacked safely are brickguards required ?
TIES
-
Have ties been tested and recorded ?
-
Are ties fixed and correctly attached ?
-
Are there a sufficient amount of ties installed ?
-
Add media
SHEETING
-
Does the scaffold require debris net or plastic weather clad ?
-
Is all debris net or weather clad fixed and secured in place correctly on the outside of the scaffold
Hand over
-
Handover complete
-
Scaffold Tag
-
Add media
DESIGN
-
Is the structure of a generic type TG20:13 compliant scaffold?
-
Does the structure have or require a design to be compliant with TG20:13 ?
NOTES
-
ANY OTHER MATTERS TO BE ADDRESSED
-
Add media
SUMMARY OF FINDINGS
-
SUMMARY, OVERALL VIEW AND RECOMMENDATIONS OF THE SCAFFOLD
ACTION DATE
-
All of the faults with the scaffold contained with in this report must be actioned within 7 days.
Alternatively the scaffold is to be put out of service and all site personnel are prohibited to use any areas not actioned.
Please provide date and signature of the person taking action: