Information
-
FFP name:
-
Conducted on
-
Prepared by
Civil
-
Have all Civil NCRs been remedied on site?
-
Has evidence of the NCRs been provided to the VPL UFB Quality Mailbox?
-
Has all reinstatement been completed? If not, please provide full details below.
-
Has all documentation, including the Pole to Boundary Data Sheet, NDF13042 and NDF245 been loaded to Viscore and checked by yourself to ensure correct?
-
Which of the Asbuilts below are loaded to Viscore and checked for accuracy?
- Lay Asbuilt
- Haul Asbuilt
- CPA (tested and passed)
Aerial Slinging
-
Does this site meet RMA requirements - IE is all cable between 150mm and 600mm of the LV?
-
Have all Aerial Slinging NCRs been rectified on site?
-
Has evidence been provided to the VPL UFB Quality Mailbox?
Fibre Jointing
-
Have all Fibre Jointing NCRs been rectified on site?
-
Has evidence been provided to the VPL UFB Quality Mailbox?
-
Which of the Asbuilts below are loaded to Viscore and checked for accuracy?
- FOG Plan
- CPA (GPON)
- CPA (Fixed Fibre)
- OFDF
-
Has the ONT testing been completed and the Splitters installed into every FFP?