Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Warehouse
QCC SOP
-
Acknowledging email is given on Customer returns is being generated after receiving from 3PL to and DEX?<br><br>Check recent Email
-
All the packages, that cannot be inbounded are being kept separate bin. (24 Hours) ?<br><br>Verify the Bins and the Date on AWB must be under SLA
-
Stamping Process is being followed after receiving of packages?<br><br>Verify Physically
-
Receiving trollies are marked with dates, to comply with FIFO?<br><br>Verify Physically
-
Email is being escalated to CS team regarrding offline (Tracking not in system) packages?<br><br>Verify recent email
-
Correct initial QC is performed and right retagged reason is selected?<br><br>Verify Physically
-
Item are being distributed by the authorized person (Runner)?<br><br>Verify Physically
-
Items are being distributed on FIFO basis?<br><br>Verify Physically
-
Items are being moved from RC to QC location before processing?<br><br>Verify Physically
-
QC agent are putting the RTC/ RTM/ RTW Scrap in their respective bin after making logistics closure?<br><br>Verify Physically
-
Runner is picking the processed item in presence of QC agent?<br><br>Verify Physically
-
Runner is reconsiling the LC location against the picked item?<br><br>Verify Physically
-
All the extra items are handed over to CS on daily basis with 24 hours?<br><br>Verify Physically
-
Decision making tool is being used to mark logistics closure?<br><br>Verify Physically
-
Seller/Customer Support is intimidated for RTV/RTC?<br><br>Check recent Email
-
All the pending cases have been escalated on Xspace wrt RTC/Scrap, RTM/Scrap, RTM > 4,000?<br><br>Verify Physically
-
During Xspace ticket, clear image of package and DM screenshot is being added?<br><br>Verify Physically
-
Processor is using his own ID?<br><br>Verify Physically
-
All the handover activity is being performed when 3PL is in QCC for pickup?<br><br>Verify Physically
-
Email is sent on handover to DEX and 3PL?<br><br>Check recent Email
-
Email is sent on handover to DEX and 3PL?<br><br>Check recent Email
-
Only those tracking are handed over to 3PL, which has been maked as 'Hand-over' in RMS?<br><br>Verify Physically
-
All the location that exist in RMS are physically available on floor?<br><br>Verify Physically
-
All the location that are physically availible on floor are tagged and have the correct items on them?<br><br>Verify Physically
-
All the trolley are properly tagged with permanent sheets?<br><br>Verify Physically
-
Weekly emails are required to be sent to management for visibility on scrap handovers?<br><br>Verify Physically
-
New RN is being generated by CS for retail item, in case of 'invalid' reason selected by customer which needs to be marked as RTC.<br><br>Verify Physically
-
For Electronics, if complaints are regarding quality issue, QC Agent will perform QC for greater than Rs.1000, else RTC for less than Rs.1000?<br><br>Verify Physically
-
QCC will be escalating an email/ Xspace ticket for further investigation of damaged/missing/wrong item, marked as scrap?<br><br>Verify Physically
-
No item is kept in the red zone/ scrap area with more than<br> one month ageing. (check on a sample basis)?<br><br>Verify Physically
-
Does not fit/ Change of mind decision is only applicable in fashion category, only if customer has selected the reason.<br> Change of mind is not applicable for some of sellers also for fashion category so this point can be excluded?<br><br>Verify Physically
-
Packages which are recieved from (DEX or 3PL) must be inbounded within same Day ?<br><br>Check in System<br>Check Tracking# in RMS and check Recieving Time must be under SLA<br><br>Check Physically<br>by checking the Package Date in the recieving Area of QCC
-
Are the inbounded Items processed within 48 Hours (3PL, DEX and other City DEX)?<br><br>Check in System<br>QCC Backlog file (Target 95%)<br><br>Check Physically<br>-Check the Backlog Trolleys<br>-Are the Stacking of Packages is Good/Bad
-
In case of RTM/RTC for High Value Item (>= Rs 10000), the case is raised to CS team for DEX within 24 hours?<br><br>Check in System<br>QCC Backlog file<br><br>Check Physically<br>-Check the Offline Inventory<br>-Are the Package stacking done properly<br>-Are the packages kept in Trolleys/Pallets
-
In case of RTM/RTC for High Value Item (>= Rs 10000), the case is raised to CS team for 3PL (SLA: 48 Hours)?<br><br>Check in System<br>QCC Backlog file<br><br>Check Physically<br>-Check the Offline Inventory<br>-Are the Package stacking done properly<br>-Are the packages kept in Trolleys/Pallets
-
No LC (logistic closure) packages kept in the 4 colour bins (RTW/RTM/RTC/Scrap) after 48 hours?<br><br>Check in System<br>QCC Backlog file<br><br>Check Physically<br>By checking the time of LC report pasted on the package
Inventory Management
-
Are all protocols for using the bin being followed as defined in the policy?
-
Are all the pallets standardized as per the protocols defined in the policy?
-
Are all the pallets standardized as per the protocols defined in the policy?
-
Are the invetory capacity levels maintained? (as defined in the policy)
-
Are the handling protocols being followed as per the policy?
-
Are the handling protocols being followed as per the policy?
Package Handling
-
Boxes/carton/package/Item is not kept on floor
-
Boxes are stacked in such a way that they don’t fall off due to imbalance with proper weight distribution
-
Fragile packages must be kept according to the correct orientation.
-
No throwing of any sort of package into trolley/carton from distance