Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
CSA
-
Price Catagory
-
Viscore/ Job Number
-
Responsible Manager
-
Auditee
-
Company
24 SSA (7455/7517)
-
24.001 SSA cable binding to hardware correct
-
24.002 SSA cable erected correctly
-
24.003 SSA cable type and size correct
-
24.006 SSA tension & sag & twist (anti dancing) correct
25 Poles
-
25.003 Pole in good condition, no splits, burs
-
25.004 Pole manufacture label in place, Pole strength minimum 6kn
-
25.005 Pole hole depth correct/Pole vertical and height correct
-
25.006 Pole positioning and spacing correct, correct face position
-
25.007 All new poles have Network pole tag installed 3mtr above ground
-
25.01 Pole safe to climb (hammer/probe/dig)
-
25.011 All metal plant hot dipped galvanised & CNSP approved
-
25.012 Plant positioned correctly and safely, plant clearances correct
-
25.017 All tagged poles in NetMAP
-
25.02 Network labelling (eg cable terminal, joint label, 124 sign) in place to suit requirements
-
25.021 Site tidy, no task waste, ground reinstatement completed
39 Aerial Terminal
-
39.001 Correct terminal used
-
39.002 Terminal mounted and secured correctly
-
39.003 Quiet Front terminal has sufficient gel
-
39.004 Terminal lid secure
-
39.005 Terminal label on lid or plate on pole
-
39.006 Lead-in entry correct
-
39.007 Lead-in terminated correctly
-
39.008 Plastic bag on multi-pair lead-in cable unused pairs
-
39.009 Cable shield installed
40 Pillar Terminal
-
40.001 Pillar - vertical, firm, depth
-
40.002 Pillar ID correct
-
40.003 Lid secure
-
40.004 Lead-in thru base only
-
40.005 Plastic bags installed & secure
-
40.006 Foam bung fitted
-
40.007 Minimum sheath height 50mm (30mm if in concrete and/or uneconomic to repair, 80mm for V3)
-
40.008 Coloured zip ties to 25 pair groups (not too tight)
-
40.009 Correct cable used
-
40.01 Correct connectors used
-
40.011 Circuit dedicated
-
40.012 Service Lead labelled correctly
-
40.013 Unused pairs capped
-
40.014 Damaged conductors repaired
-
40.015 Faulty connectors replaced
-
40.016 Encapsulated loop resealed correctly
-
40.017 V3: Lead-in customer and network labels OK
-
40.018 Green cable tie on exchange side
-
40.021 Connectors >50mm from ring cut
-
40.022 Site tidy, no task waste
41 BDD Terminal
-
41.003 Radi: Base & lid clean, O ring seated correctly, O ring replaced upon entry
-
41.004 O/J lid labelled
-
41.005 Radi is correctly installed, thermal change and lead in
-
41.006 2m loops at BDD pits
-
41.007 2m insulated tail installed at last BDD
-
41.008 Plastic bags installed & secure
-
41.009 Coloured ties to 25 pair groups
-
41.01 Correct cable used
-
41.011 Correct connectors used
-
41.012 Circuit dedicated
-
41.013 Service Lead labelled correctly
-
41.014 Unused pairs capped
-
41.015 Damaged conductors repaired
-
41.016 Faulty connectors replaced
42 PDS Terminal
-
42.005 Designed pair arrangement correct
-
42.006 QF terminal labelling correct
-
42.007 QF terminal secured to backing plate
-
42.008 Foam bung fitted
-
42.009 Adequate gel in quiet front
-
42.01 Service Leads installed correctly
-
42.011 Service Lead labelled correctly
43 Aerial Service Lead
-
43.001 Correct Service Lead used
-
43.002 No In span joints
-
43.003 Tension, sag and twist correct
-
43.004 Correct pole fittings used and installed (screw eyes, sash clamps)
-
43.005 Lead-ins enter terminal correctly
-
43.006 White pipe down poles
-
43.007 600mm saddle spacing or 1500mm bandit spacing
-
43.008 Roadway crossing min 5.5m height, elsewhere 4.25 metre height
-
43.009 Loops on poles tied
-
43.011 Lightning protection runs >500 metres
-
43.012 Correct building fittings used (screw eyes, sash clamps)
44 Buried Service Lead
-
44.001 Service Lead terminated correctly
-
44.002 20mm pipe connected at Pedestal correctly - (bend into pedestal)
-
44.003 20mm pipe connected at BDD correctly (50mm into BDD pit, 450mm deep)
-
44.004 20mm pipe connected at RLG correctly (at base of DP, bend if room)
-
44.005 Individual pipe & cable for installs of <100 metre
-
44.006 Direct buried cable option (no pipe) for > 100 metre
-
44.007 Green 20mm installed in trench
-
44.008 White pipe above ground level
-
44.009 Depth correct (450mm cover)
-
44.01 Power/ Gas clearances correct
-
44.011 Cable & pipe repair correct
-
44.012 Reinstatement/ backfill satisfactory
-
44.013 Pipe connected at ETP correctly (not glued)
-
44.014 Overlay of Service Lead justified
55 Network Records
-
55.085 FRE generated to capture faults (where appropriate)