Pre Work Inspection ( to be completed prior to beginning work)
-
Plans have been picked up and signed for.
-
Purchase order has been received or picked up.
-
Work area is clean and free of debris, ready to dig lines.
-
Foundation is complete, and pad area is ready.
-
Electricity is at site.
-
Site Superintendent:
-
Trade Contractor: Company Name (printed)
Final inspection: ( to be completed before Trade Contractor leaves job site)
-
Plumbing is in slab, and capped and protected as required.
-
Checked placement of pipes.