Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Checklist
-
19 mm Compressed cement sheet flooring
-
100 mm Structural step down in Balcony to house/ Please contact technical support team, if step down is less than 100 mm, please contact TS team
-
Flooring has been nailing to balcony joists using 2.8 x 50mm FC nails 3 50mm D Head gun nails
-
Flooring Sheet Control Joints at every 2.7 m interval (Every 3 Sheets)
-
Marked the Balcony floor waste in by Site supervisor (Any location is within 2 m from balcony floor waste and floor waste to sliding door maximum distance 1.5 m
-
200 mm wide Balcony overflow installed 70 mm above the Structural floor level.
-
Balcony edge flashing install with 150 mm with upstand
-
Flashing in under the sliding door/other door area with 25 mm upstand in three side
-
Waterproof has been done under the sliding door area (Flashing is only a substrate)
-
Timber blocking has been provided under the Balcony balustrade post location under the flooring.
-
Any parapet wall with balustrade on top, please provide minimum 3 Nos/90X45 top plate with sufficient connection to main frame
-
Screed top level next to sliding doors are 65 mm less than the house (Liveable area) structural floor level (10 mm thick tile)
-
Final tile finish 50 mm less than the house (Liveable area) structural floor level at sliding door area
-
WU approved Water proofing Product has bene used
Comments
-
Comments
-
Media
Sign Off
-
Supervisor Signature
-
Date and Time