Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Checklist
-
Install wall waste plumbing including puddle flanges (Puddle Flanges are not required for tile tray / Vedi waterproof system)
-
Water hot and cold power rough in completed the shower mixer location and product as per C&M and wet area plan. (Please keep wet area plan copies at site)
-
Surface clean; free of dust, dirt, oil, grease, paint, curing compounds, concrete sealers, loosely bonded toppings, old adhesive residues
-
Water proofing application completed
-
Contractor is using Westurban approved (WPA/Gripset/Ardex) Please upload images of products including primer
-
Wall and floor substrate are comply product as per Australian Standard
-
Ensure all pipe penetrations and angles are appropriately detailed (polyurethane or similar) to create fillet/cove.
-
Wall/wall, wall/floor junctions and other areas where movements is expected are also appropriately detailed (polyurethane or similar) to create fillet / cove
-
Polyurethane or similar sufficiently cured prior to waterproofing application
-
1800mm high wall water proofing in shower areas and 150mm water proofing rest of area
-
Waterproofing applied at recommended thickness (i.e 0.4-0.5mm) per coat
-
Number of waterproofing coats applied as per manufacturer's guidelines
-
Barricade entrance to prevent entry by site personnel
-
Protect work against drafts during installation and again for at least 72 hours after completion to prevent damages to substrates, installation products and flooring materials
-
Waterproofing sufficiently cured prior to proceeding with follow coat / screeding / other application
-
Screeding is provided in shower area and slope 1:100
Comments
-
Comments
-
Media
Sign Off
-
Supervisor signature
-
Date and Time