Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Checklist
-
TBM has been marked by Land surveyor
-
Concrete follows the Approved slab plan for set out
-
Under slab insultations has been installed as per Plan
-
Minimum Brick Rebate height is 190mm set in framework
-
Deepen rebate provide as per final external ground finish level/ Clear direction to concretors
-
Starter bars for Retaining wall has been installed
-
All electrical and PLumbing Conduit are provided for island bench with Basin/Cook Top/Dish washer
-
External service conduits are installed in Slab area. (Gas, NBN)
SITE
-
Check site cut (R.L) and floor level (R.L) as per site plan
-
Does the actual site fall resemble contour markings on the site plan
-
Is the Set Out Correct as per set out plan
-
Is the founding material as per the soil report
-
Was rock encountered during excavations
-
Is Spoil removal required
-
Does the site require sub-surface drainage during construction
-
Has the crosser over and footpath been damaged
-
Does the Site Bin need to be emptied
SLAB
-
Are Bored Piers/ Screw Piles installed correctly and as per plan
-
Are all "Over All" measurements correct and as per plan
-
Are all bar chairs installed
-
Are all rebates correct and as per plan
-
Is additional binding required
-
Are all Pads screeded correctly and compacted
-
Is the slab correct thickness as per plan
-
Have all Hobs been accounted for
-
Is the garage step down correct? as per plan
-
Is the porch step down correct and as per plan
-
Are all starter bars installed and as per plan
-
Are all shower 40mm step downs installed?? as per Engineering
-
Have all slab step downs been check measured and are completed as per plan
-
Is a line pump required
-
Is a spotter required for slab pour
-
Is in slab insulation required
-
Is in slab hydronic heating required? and engineering reflecting this
-
Is the meter box installed as per plan? and power connection called up
Drains
-
Are all pit heights correct and as per plan
-
is the kitchen electrical conduit installed for island bench
-
Are all pits installed in the right locations as per civil plans
-
Have all drains been lagged
-
Are all stacks installed in correct locations
-
Has the Drain Camera check been completed? and all breaks rectified
-
Are there in drains installed along and inside the trenches
Retaining Walls
-
Are all retaining walls installed as per plan
-
Are all retaining walls installed at the correct height
-
Are there any additional retaining walls required
-
Have all retaining walls been waterproofed correctly and aggy pipes installed
-
Upload images for future reference
Comments
-
Comments
-
Media
Sign Off
-
Supervisor Signature
-
Date and Time