Information

  • H2B CRANES/PILING RIGS .

  • Project Name: Tabulam New Bridge.

  • Location: BRUXNER HIGHWAY TABULAM

  • Contractor

  • Prepared by

  • Conducted on

Work Activity Record

  • N.A Not Applicable. N.C Not Checked

  • 1<br>Does the unit and its accessories/attachments comply with Annexure G22/J – Truck and Plant Requirements?

  • 2<br>Is the unit and its attachments/accessories design compliant and covered in accordance with the AS 2550 and AS 1418?

  • 3<br>Does the item require NSW WorkCover design and or item registration in accordance with Appendix A in WorkCover publication “Guidance For The Provisions Of Cranes, Hoists And Winches Under WHS Legislation In NSW”?

  • 4<br>Is the item currently item registered with WorkCover?

  • 5<br>Does the item have a current CraneSafe registration certificate?

  • 6 <br>Has a risk assessment been conducted on any attachments or accessories that have or can be fitted to the unit that may change the purpose for which the unit was designed or increased or added any risks and/or hazards?

  • 7<br>Has and will the unit be submitted to arduous working conditions, and if so, has and will the maintenance and inspection schedules reflect the necessary requirements?

8 Has and will the item receive/d servicing and inspections, as a minimum, to the requirements of AS 2550.1, such as:

  • :<br> Pre-operational inspection,<br><br>

  •  Routine inspection and maintenance,

  •  Periodic inspections,

  •  major inspection to assess a crane for continued safe operation and assessment for changed operation?

  • 9<br>Are historic, or at least the previous 12 months, service or maintenance records, and the logbook/s from the unit and its accessories and attachments available for inspection?

  • 10<br>If the unit or any mechanical part of it is greater than ten years old or any structural part is greater than 25 years old or any part of it has exceeded its design life, has a major inspection to AS 2550.1 been completed to assess the suitability for continued safe service of the unit or part?

  • 11<br>Were repairs or modifications that had been carried out done to the AS 2550 and AS 1418?<br>

  • 12<br>If repairs or modifications are to be carried out they will be done to the AS 2550 and AS 1418?

  • 13<br>Is there a daily inspection log book kept in the unit at all times?

  • 14<br>Are load cells, load moment indicators and limit switches e.g. over wind or anti-two-block devices fitted to the unit?

  • 15<br>Have these load cells, load moment indicators and limit switches been inspected and tested within the last 12 months?

  • 16<br>Have winch ropes been correctly anchored to the drums?

  • 17<br>Has all lifting equipment, attachments and accessories including but not limited to slings, hooks, eyes, beams, shackles, blocks and chains been inspected, tested and passed for use according to a certified and established procedure?

  • 18<br>Are the cranes rating and load capacity charts approved and applicable to the unit, its attachments, its accessories, its use and site conditions?

  • 19<br>If the crane has free fall capability, is there a physical locking system in place that disables the free fall capability?

  • 20<br>Has a weekly test procedure been prepared and established for the free fall physical locking system?

  • 21<br>Have controls been put in place for freefall work?

  • 22<br>Are erection, commissioning and dismantling instructions compliant with AS 2550.1 for cranes in place?

  • 23<br>Has a procedure been established for the completing of the daily risk assessment of the crane set up and foundations?

  • 24<br>Has a risk assessment been prepared for the operations the crane will perform?

  • 25 <br>Has a movement plan and risk assessment been prepared for the crane considering such things as loadings, side loadings, conditions, terrain and direction not excluding other matters to ensure safety of the crane, personnel and equipment while walking, travelling or moving on site?

  • 26<br>Has an accident recovery procedure for risk assessments categorised as high risk been established and put in place?

  • 27<br>Has training for the accident recovery procedure been undertaken and successfully completed?

  • 28<br>Where the crane is vessel mounted, does it fully comply with AS 2550.1 section 6.29?

  • 29<br>Is there documented evidence available for all of the above?

  • 30<br>Where piling is to be undertaken, has section 6.5 of AS 2550.5 been totally addressed?

Compliance and Follow-up action.

  • Is the activity compliant.

  • Surveillance Officer

  • NCPN or memo number.

  • Follow up action

  • Product Non Conformance

  • System Non Conformance

  • Contractor generated NCR

  • Contractor generated a CAR

Matters arising

  • NCPN no

  • Contractors NCR no

  • CAR no

  • Closed out.

  • RMS representative's name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.