Final checks.
-
Have you gas tested for a minimum of five minutes?
-
Is the gas meter at least 1m away from an appliance or an openable window?
-
Is the gas meter positioned clear of a downpipe?
-
Is there an LPG bottle set up on this property, and if so, have all clearances been met?
-
Are all noggins secure and free from movement?
-
Are all noggins set back at 40mm?
-
Are all lugged elbows and tap sets screwed back securely and free from any movement?
-
Have you check that no metal bracing is touching pipe work at all?
-
Have you checked every fixture for cross connections?
-
Have the solar panels been installed and the flow and return lines connected?
-
Are all flow and return lines clear of touching any plastic pipes or wiring?
-
Is the ORG charged correctly?
-
Is the rough in pressurised?
-
Have all wastes been cut off neatly and in pipe reducers fitted?
-
Has the vent been run at the opposite end of the sewer point, ensuring that there are no unvented branches exceeding 10m?
-
Has the vent been flashed?
-
Have all bath and shower wastes been connected?
-
Have you tested all bath and shower connections by pouring at least 40 liters down them?
-
Are all bath and shower wastes free from leaks?
-
If there are tiled shower bases, have you poured water down the riser and confirmed that the DT is holding water?
-
Have all shower boxes been packed with sand, filled with a minimum of 100mm of concrete mix and finished smooth and level with the slab?
-
Are all toilet risers centered?
-
If there is a spa bath, have you ran the suction, flow & air line out to the pump position?
-
Are all the roof flashings complete and the roof water tight?
-
Are all downpipes completed?
-
Have all downpipes been installed plumb and checked with a level over its entire length?
-
Have all downpipes been connected to the stormwater?
-
Are all downpipes riveted in the centre through the pop?
-
Have all downpipe stormwater connections got at least 250mm cover?
-
Are all downpipe adaptors straight and 75mm above finish ground level?
-
Have you checked the plans & job cards for any extra inclusions?
-
Has all rubbish been picked up, placed in a bin provided and secured so it does not blow away?
-
Have all external windows and doors been locked?
-
Has the site been left in a safe state with all site fences closed?
-
Notes-
-
Add media
-
Is this job ready for the next stage?
-