Information

  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Final checks.

  • Have you gas tested for a minimum of five minutes?

  • Is the gas meter at least 1m away from an appliance or an openable window?

  • Is the gas meter positioned clear of a downpipe?

  • Is there an LPG bottle set up on this property, and if so, have all clearances been met?

  • Are all noggins secure and free from movement?

  • Are all noggins set back at 40mm?

  • Are all lugged elbows and tap sets screwed back securely and free from any movement?

  • Have you check that no metal bracing is touching pipe work at all?

  • Have you checked every fixture for cross connections?

  • Have the solar panels been installed and the flow and return lines connected?

  • Are all flow and return lines clear of touching any plastic pipes or wiring?

  • Is the ORG charged correctly?

  • Is the rough in pressurised?

  • Have all wastes been cut off neatly and in pipe reducers fitted?

  • Has the vent been run at the opposite end of the sewer point, ensuring that there are no unvented branches exceeding 10m?

  • Has the vent been flashed?

  • Have all bath and shower wastes been connected?

  • Have you tested all bath and shower connections by pouring at least 40 liters down them?

  • Are all bath and shower wastes free from leaks?

  • If there are tiled shower bases, have you poured water down the riser and confirmed that the DT is holding water?

  • Have all shower boxes been packed with sand, filled with a minimum of 100mm of concrete mix and finished smooth and level with the slab?

  • Are all toilet risers centered?

  • If there is a spa bath, have you ran the suction, flow & air line out to the pump position?

  • Are all the roof flashings complete and the roof water tight?

  • Are all downpipes completed?

  • Have all downpipes been installed plumb and checked with a level over its entire length?

  • Have all downpipes been connected to the stormwater?

  • Are all downpipes riveted in the centre through the pop?

  • Have all downpipe stormwater connections got at least 250mm cover?

  • Are all downpipe adaptors straight and 75mm above finish ground level?

  • Have you checked the plans & job cards for any extra inclusions?

  • Has all rubbish been picked up, placed in a bin provided and secured so it does not blow away?

  • Have all external windows and doors been locked?

  • Has the site been left in a safe state with all site fences closed?

  • Notes-

  • Add media

  • Is this job ready for the next stage?

  • I have checked all the above items and the work has been done to a satisfactory standard.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.