Information
-
Audit Title
-
Audit No
-
Analyst
-
Project Manager
-
Reason for Audit
-
Is this person now authorised ?
-
Number of Non Compliances
-
Date of audit
-
Client
-
Site Address
-
Job Number
-
Location and description of works being undertaken
Project Manager - Contract review and planning
-
Has the job number been set up on Tracker correctly ?
-
Are details found in the method statement correct regards the outlined scope of works and requirements for the client ?
-
Has a method statement and risk assessment been accurately completed and signed by the PM?
-
Has all paperwork used by the project manager the latest controlled documents ? Please state them
-
Where the work is project managed has the analyst been provided with all relevant required information like the the latest survey/re-inspection information/Specification ?
-
Where the work is being project managed is the type of works suitably planned and in line with current regulations and guidance ?
-
Is the analyst suitably trained for the tasks undertaken ? Auditor to only authorise staff with evidence of appropriate experience and training
Analyst - Health and Safety and Quality Control
-
Is all required PPE on site ie Hard hats ,Boots, Gloves, HI Viz jacket, goggles ear defenders and disposable overalls and booties if required ?
-
Is the RPE being used in good condition , complete , clean and suitably identified as the analysts mask ? Is the surveyor clean shaven and can demonstrate a good face fit ?
-
Has the analyst filled in his monthly exposure sheet and equipment records and are they up to date ?
-
Is there a copy of the Quality manual, M&S guidance and Hsg 248 & 247 available ?
-
Is the analyst up to date with his their monthly QC's
-
Are filters being used Media/Lab blanked ? Record details / results
-
Are calibration graphs available for the flow meters ?
-
Does the surveyor have copies of all relevant training records available and are they in date ? P402 ,CSCS ,face fits and WAH etc
-
Are COSHH assessments available ?
-
Has a risk assessment been completed ,signed , reviewed and updated where required ?
Analyst - Equipment
-
Is there an adequate number of calibrated pumps and their chargers available ?
-
Has equipment been PAT tested in past 12 months ? Are all cables in good condition and free of tape marks
-
Is there adequate number of cowls and caps present and are they clearly identified ?
-
Is there a calibrated personal pump and a charger available on site?
-
Sufficient clean acetone and triacetate available ?
-
Is there a Vaporiser present ?
-
Tweezers and syringes present ?
-
Adequate amount of slides and cover slips ?
-
Lens tissues and wet wipes available ?
-
Chisel or Screwdriver, torch with spare batteries and a mirror available ?
-
Sample bags available ?
-
Spare fuses and bulbs available ?
-
Microscope being used suffice ? What is the ref number & the next service date?
-
Central telescope present ?
-
Stage micrometer being used ? What is the ref number & the next calibration date ?
-
NPL test slide being used ? What is the red number & the next calibration date?
-
Watch and barometer number used ? What is the ref number & the next calibration date?
-
High Flow meter used ? What is the ref number and next calibration date ?
-
Low flow meter used ? What is the ref number and next calibration date ?
-
That months slide box at hand and in order ?
Analyst- Air Monitoring
-
Does the analyst use a lab van and if so does the lab van comply with the quality manual ? Check for fire extinguisher and bulkhead etc
-
Is the lab area suitable and clean ?
-
Has a lab air test been conducted where required ?
-
For general air monitoring has the analyst reviewed the contractors method statement and understood it ?
-
Has a field blank been conducted ? If required to count what was the result
-
Was filter loading and the initial set up of the air test ok ?
-
What type of air test was witnessed and was it suitably conducted ?
-
Can the Analyst demonstrate the setup of the microscope correctly ?
-
Was filter preparation and slide mounting suitable ?
-
Where witnessed was counting conducted suitably as per HSG 248 ?
-
Where possible has the auditor cross checked 2 slides ? Was the count very different ?
-
We're all other aspects of daily checks and monitoring conducted correctly where we are required to do so?
-
For general air monitoring / previous shifts has paper work been filled in correctly and all sample times , info and calculations correct ?
-
Was a visual check carried out if required to ensure the scope of works has been completed ? The depends on the clients request or duty of care
-
Was a non licensed report required and filled in correctly if requested by the client / PM ?
Summary
-
Please summarise the audit and give any recommendations moving forward.
Project Managers Result
-
Score
-
Audit Result -Satisfactory or Non satisfactory
Analyst Result
-
Score
-
Audit Result -Satisfactory or Non satisfactory
-
Analyst Name and Signature
-
Auditor Name and Signature