Information

  • Audit No

  • Analyst

  • Reason for Audit

  • Number of Non Compliances

  • Date of Audit

  • Client

  • Site Address

  • Job Number

  • Location and description of works ( material )

Analyst - Reoccupation Certificate Stage 1

  • Has the analyst reviewed the contractors method statement and understood it ?

  • Has the analyst conducted a suitable risk assessment before proceeding ?

  • Has the analyst produced an accurate plan and has it been signed by the supervisor to agree the work ? Ensure plans meet guidance in HSG248

  • Has the analyst checked the DCU and is it set up correctly ?

  • Has the skip or waste area, applicable waste / transit routes and the immediate surrounding area to the enclosure been checked correctly and free from obvious asbestos debris and waste ?

  • Has the enclosure integrity been checked and is the NPU intact and running ?

  • Has viewing of the work area via the viewing panel / CCTV been carried out and any potential issues addressed ?

  • Has the analyst filled in stage 1 paperwork correctly ?

  • Has the analyst used the DCU to enter the enclosure ?

Analyst - Reoccupation Certificate Stage 2

  • Has the analyst taken in a mirror , torch and screw driver into the work area for the visual ?

  • Had the analyst done an initial inspection of the work area to confirm the visual can be adequately be carried out ?

  • Is the enclosure dry ?

  • Was the visual thorough and carried out to a satisfactory standard ?

  • Did the analyst use access equipment correctly ?

  • Did the analyst instruct the contractors / supervisor correctly on an remedial actions ?

  • Was any remaining ACMS identified and where applicable suitably encapsulated ?

  • Has all generated waste and work tools been removed from the work area ?

  • Has decontamination been carried out correctly ?

  • Has the paperwork for stage 2 been completed correctly ?

Analyst - Reoccupation Certificate Stage 3

  • Has the NPU been turned off where applicable and capped ?

  • Has a field blank been conducted , if counted please record result ?

  • Has the analyst used the correct number of air tests for the size of the enclosure ? Record number used and volume of area

  • Has the set up of the pumps been correct and all details recorded correctly ?

  • Has disturbed air testing been carried out correctly with a brush and for a minimum of 1.5 mins per pump ?

  • Has the retrieval process of pumps from the work area been carried out correctly and details recorded correctly ?

  • Was decontamination carried out satisfactory ?

  • Can the Analyst demonstrate the setup of the microscope correctly ?

  • Was filter preparation and slide mounting suitable ?

  • Where witnessed was counting conducted suitably as per HSG 248 ?

  • Has Stage 3 paperwork been filled in correctly ?

Analyst - Reoccupation Certificate Stage 4

  • Has the analyst watched parts of stage 4 to monitor if there has been dust and debris released during de-sheeting ?

  • Has the analyst run a reassurance where there is justification to do so ?

  • Has the analyst carried out a thorough inspection of the former work area and its associated routes to ensure no debris ,waste , equipment or former enclosure materials remain ?

  • Has any known asbestos or further uncovered potential asbestos been uncovered and been dealt with correctly ?

  • Has the paperwork been completed correctly for stage 4 and signed by the removal contractor representative?

Analyst - DCU Clearance

  • Has the analyst worn the correct RPE and PPE for the clearance ?

  • Has the visual been satisfactory ?

  • Has the air test been conducted correctly ?

  • Was a disturbance done for the air test and how ?

  • Was the paperwork completed for the DCU correctly ?

Summary

  • Please summarise the audit and give any recommendations moving forward.

Analyst Result

  • Audit Result - Satisfactory or Non Satisfactory

  • Score

  • Analysts Name and Signature

  • Assessor Name and Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.