Information
-
Inspection Title. B80 Concrete Placement
-
Project Name: Tabulam New Bridge.
-
Location: BRUXNER HIGHWAY TABULAM
-
Contractor
-
Prepared by
-
Conducted on
Work Activity Record
3 DESIGN OF CONCRETE MIXES
-
Cl 3.4 Has the curing method been agreed and is the material onsite.
-
Cl 3.8.1 Has the Hold Point for the mix design been released.
-
Cl 3.8.1 HOLD POINT
CL 4 SUPPLY and DELIVERY of CONCRETE
-
Cl 4.1 Has the conforming mix type concrete been delivered.
-
Cl 4.3.4 Have all concrete batches been delivered with a delivery docket containing the details listed in this clause (see Tables section)
-
Cl 4.35 Has the concrete been placed and compacted with 1.5 hours from batch (unless otherwise approved).
-
Cl 4.4 Have all loads delivered been slumped.
-
Cl 4.5 Has water only been added onsite if:<br>It is less than 45 minutes from batch. <br>Correct retempering procedure followed <br>The amount of water added recorded.<br>The load is re slumped.
-
Cl 4.6 Is the temperature of the concrete within range 10 deg C to 32 deg C.<br>For precast and cast-in-place piles 5 deg C to 35 deg C. <br>
6 SUPPLY AND FIXING OF STEEL REINFORCEMENT AND EMBEDMENTS
-
Cl 6.3.1 Has the reinforcement been fabricated as per the drawings and been placed with the correct cover.
-
Cl 6.7.2 Has the reinforcement supports been correctly positioned and secure.
7 PLACING, COMPACTING, FINISHING AND CURING OF CONCRETE
-
Cl 7.1 Has the concrete been placed, compacted, finished and cured so as to:<br>(a) prevent segregation or loss of materials
-
(b) Prevent premature stiffening.
-
(c) Prevent nonconforming displacement of reinforcement, fitments or embedments.
-
(d) Produce a dense homogeneous product which is monolithic between planned joints and/or the extremities of members, or both.
-
(e) Completely fill the formwork to the intended level, expel entrapped air, and surround all reinforcement, tendons, ducts, anchorages and embedments.
-
(f) Provide the specified finishes.<br>
-
(g) Control cracking, including that caused by plastic and drying shrinkage, concrete slumping, plastic settlement, crusting and thermal gradients.
-
Cl 7.1 Has the HOLD POINT been released.
-
Cl 7.3 Has the HOLD POINT been released
-
Cl 7.3 HP
-
Cl 7.4.2 Has the method of concrete placement met the following requirements. <br>(a) Concrete evenly placed in one continuous operation
-
Has the HOLD POINT released.
-
Cl 7.3A HP
-
7.4.2 (b) Concrete dropped from a height that segregation cannot occur.
-
Cl 7.4.3 Concrete vibrated correctly, using a sufficient number of vibrators.
-
Cl 7.5 Unless the principal approves special precautions , all concrete other than cast-in-place piles must not be placed if the air temperature in the shade is:<br>Below 5 deg C or above 38 deg C. <br>Predicted to be below 5 deg C in the 24 hours after placement.
-
Cl 7.5 For cast-in-place piles do not place concrete if<br>Ice exists on pile casings, embedments, steel reinforcement or in the pile holes.
-
Cl 7.8 Has all free water been removed from the area where concrete is to be placed. <br>If not then place in water using tremie concrete in accordance with Specification RMS B58 or RMS B59. <br>Do not place in water below 5 deg C.
-
Cl 7.9 Surface of construction joints must have;<br>Surface roughness not less than 3mm. <br>All loose material removed.
-
Cl 7.11.2 Deck and Approach Slab Surfaces. <br>Have the surfaces been finished using a vibrating screed on rails, suspended above reinforcement.
-
Cl 7.11.2.5.Is the finishing type either by wood floating or steel trowelling followed by sweeping. Is the quality of concrete finish acceptable.
-
Cl 7.12.1 Is the curing in accordance with the curing regime nominated in item (d) of clause 3.8.2
-
Cl 7.12.1 <br>Have all cast in place bridge decks or approach slabs for a minimum of 72 hours after finishing operations are completed.
-
Cl 7.12.2 Wet Curing: concrete must be wet and covered with canvas, hessian, geofabric with plastic sheeting, or other suitable materials and be kept wet continuously.
-
Cl 7.12.3.2 Curing compounds must conform to AS 3799 for Classes and Types specified in Table B80.18.
-
Cl 7.15 EARLY TRAFFICKING of BRIDGE DECKS
-
CL 7.15 HAS THE HOLD POINT been released.
8 PROPERTIES OF HARDENED CONCRETE
-
Cl 8.1 Have methods and frequencies of sampling and testing of concrete been in accordance with Annexure B80/L
5 FORMWORK
-
CL 5.9.2 Has formwork been stripped on or after the date that concrete achieved the required compressive strength.
As per table B80.12 -
Cl 5.9.2 Date formwork can be stripped.<br>Date formwork was stripped.
G22 Safety and G36 Environmental
G22 SAFETY
-
Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>
-
Has a SWMS been developed.
-
Has a certified rigger checked that the structural members are secure before the load is released.
-
Is each and every item of plant being used for its designated and intended purposes.
-
Have the attachments for plant and processes been approved and used in accordance with their design and purposes.
-
Is the correct PPE being worn
-
Have scaffolds and falsework been erected safely and signed off by qualified personnel where applicable.
-
Are all accesses safe and sign posted.
-
Are the Worker on Foot procedures being followed.
-
Are all plant and vehicles fitted with beacons, reversing alarms and cameras where required.
-
Is all electrical equipment tested and tagged and in good condition.
-
Were any unsafe practices observed. <br>
-
Good safe practices observed.
G36 ENVIRONMENTAL
-
Are Erosion and Sediment controls measures being installed and maintained.
-
Have nearby/adjacent waterways been protected from potential concrete, grout and curing compound spills.
-
Has a concrete washout area/s been defined and used.
-
Has mud been prevented from being deposited on roadways.
-
Have any environmental incidents or potential incidents been observed.
-
Good environmental procedures observed.
Compliance and Follow-up action.
-
Is the activity compliant.
-
Surveillance Officer
-
NCPN or memo number.
-
Follow up action
-
Product Non Conformance
-
System Non Conformance
-
Contractor generated NCR
-
Contractor generated a CAR
Matters arising
-
NCPN no
-
Contractors NCR no
-
CAR no
-
Closed out.
-
RMS representative's name
Tables
-
Cl 4.3.4
-
Table B80.18