Information

  • Inspection Title. B80 Concrete Placement

  • Project Name: Tabulam New Bridge.

  • Location: BRUXNER HIGHWAY TABULAM

  • Contractor

  • Prepared by

  • Conducted on

Work Activity Record

3 DESIGN OF CONCRETE MIXES

  • Cl 3.4 Has the curing method been agreed and is the material onsite.

  • Cl 3.8.1 Has the Hold Point for the mix design been released.

  • Cl 3.8.1 HOLD POINT

    Capture.PNG 55.PNG

CL 4 SUPPLY and DELIVERY of CONCRETE

  • Cl 4.1 Has the conforming mix type concrete been delivered.

  • Cl 4.3.4 Have all concrete batches been delivered with a delivery docket containing the details listed in this clause (see Tables section)

  • Cl 4.35 Has the concrete been placed and compacted with 1.5 hours from batch (unless otherwise approved).

  • Cl 4.4 Have all loads delivered been slumped.

  • Cl 4.5 Has water only been added onsite if:<br>It is less than 45 minutes from batch. <br>Correct retempering procedure followed <br>The amount of water added recorded.<br>The load is re slumped.

  • Cl 4.6 Is the temperature of the concrete within range 10 deg C to 32 deg C.<br>For precast and cast-in-place piles 5 deg C to 35 deg C. <br>

6 SUPPLY AND FIXING OF STEEL REINFORCEMENT AND EMBEDMENTS

  • Cl 6.3.1 Has the reinforcement been fabricated as per the drawings and been placed with the correct cover.

  • Cl 6.7.2 Has the reinforcement supports been correctly positioned and secure.

7 PLACING, COMPACTING, FINISHING AND CURING OF CONCRETE

  • Cl 7.1 Has the concrete been placed, compacted, finished and cured so as to:<br>(a) prevent segregation or loss of materials

  • (b) Prevent premature stiffening.

  • (c) Prevent nonconforming displacement of reinforcement, fitments or embedments.

  • (d) Produce a dense homogeneous product which is monolithic between planned joints and/or the extremities of members, or both.

  • (e) Completely fill the formwork to the intended level, expel entrapped air, and surround all reinforcement, tendons, ducts, anchorages and embedments.

  • (f) Provide the specified finishes.<br>

  • (g) Control cracking, including that caused by plastic and drying shrinkage, concrete slumping, plastic settlement, crusting and thermal gradients.

  • Cl 7.1 Has the HOLD POINT been released.

  • Capture.PNG 54.PNG
  • Cl 7.3 Has the HOLD POINT been released

  • Cl 7.3 HP

    Capture.PNG 53.PNG
  • Cl 7.4.2 Has the method of concrete placement met the following requirements. <br>(a) Concrete evenly placed in one continuous operation

  • Has the HOLD POINT released.

  • Cl 7.3A HP

    Capture.PNG 52.PNG
  • 7.4.2 (b) Concrete dropped from a height that segregation cannot occur.

  • Cl 7.4.3 Concrete vibrated correctly, using a sufficient number of vibrators.

  • Cl 7.5 Unless the principal approves special precautions , all concrete other than cast-in-place piles must not be placed if the air temperature in the shade is:<br>Below 5 deg C or above 38 deg C. <br>Predicted to be below 5 deg C in the 24 hours after placement.

  • Cl 7.5 For cast-in-place piles do not place concrete if<br>Ice exists on pile casings, embedments, steel reinforcement or in the pile holes.

  • Cl 7.8 Has all free water been removed from the area where concrete is to be placed. <br>If not then place in water using tremie concrete in accordance with Specification RMS B58 or RMS B59. <br>Do not place in water below 5 deg C.

  • Cl 7.9 Surface of construction joints must have;<br>Surface roughness not less than 3mm. <br>All loose material removed.

  • Cl 7.11.2 Deck and Approach Slab Surfaces. <br>Have the surfaces been finished using a vibrating screed on rails, suspended above reinforcement.

  • Cl 7.11.2.5.Is the finishing type either by wood floating or steel trowelling followed by sweeping. Is the quality of concrete finish acceptable.

  • Cl 7.12.1 Is the curing in accordance with the curing regime nominated in item (d) of clause 3.8.2

  • Cl 7.12.1 <br>Have all cast in place bridge decks or approach slabs for a minimum of 72 hours after finishing operations are completed.

  • Cl 7.12.2 Wet Curing: concrete must be wet and covered with canvas, hessian, geofabric with plastic sheeting, or other suitable materials and be kept wet continuously.

  • Cl 7.12.3.2 Curing compounds must conform to AS 3799 for Classes and Types specified in Table B80.18.

  • Cl 7.15 EARLY TRAFFICKING of BRIDGE DECKS

    B80 CL 7.15 HP
  • CL 7.15 HAS THE HOLD POINT been released.

8 PROPERTIES OF HARDENED CONCRETE

  • Cl 8.1 Have methods and frequencies of sampling and testing of concrete been in accordance with Annexure B80/L

5 FORMWORK

  • CL 5.9.2 Has formwork been stripped on or after the date that concrete achieved the required compressive strength.
    As per table B80.12

    Capture.PNG 51.PNG
  • Cl 5.9.2 Date formwork can be stripped.<br>Date formwork was stripped.

G22 Safety and G36 Environmental

G22 SAFETY

  • Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>

  • Has a SWMS been developed.

  • Has a certified rigger checked that the structural members are secure before the load is released.

  • Is each and every item of plant being used for its designated and intended purposes.

  • Have the attachments for plant and processes been approved and used in accordance with their design and purposes.

  • Is the correct PPE being worn

  • Have scaffolds and falsework been erected safely and signed off by qualified personnel where applicable.

  • Are all accesses safe and sign posted.

  • Are the Worker on Foot procedures being followed.

  • Are all plant and vehicles fitted with beacons, reversing alarms and cameras where required.

  • Is all electrical equipment tested and tagged and in good condition.

  • Were any unsafe practices observed. <br>

  • Good safe practices observed.

G36 ENVIRONMENTAL

  • Are Erosion and Sediment controls measures being installed and maintained.

  • Have nearby/adjacent waterways been protected from potential concrete, grout and curing compound spills.

  • Has a concrete washout area/s been defined and used.

  • Has mud been prevented from being deposited on roadways.

  • Have any environmental incidents or potential incidents been observed.

  • Good environmental procedures observed.

Compliance and Follow-up action.

  • Is the activity compliant.

  • Surveillance Officer

  • NCPN or memo number.

  • Follow up action

  • Product Non Conformance

  • System Non Conformance

  • Contractor generated NCR

  • Contractor generated a CAR

Matters arising

  • NCPN no

  • Contractors NCR no

  • CAR no

  • Closed out.

  • RMS representative's name

Tables

  • Cl 4.3.4

    Cl 4.3.4
  • Table B80.18

    no label
The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.