Calorifiers & Heat Exchangers

  • Type of Service Conducted

Quarterly Checks

Heat Exchangers

  • Examine and clean strainers

Calorifiers

  • Note hot water storage temperature and log. Adjust as necessary to achieve temperature of 60ºC.

  • Check setting of each thermostat (where fitted). Re-adjust/recalibrate where required and log

  • Check all valves and draincocks for correct operation and report any defects immediately.

  • Check operation of HWS primary controls, where fitted, re-adjust where necessary

  • Check manhole cover, bolt head and access covers for correct fit an any signs of leakage and nip up as necessary

  • Check and log water temperatures at 25% taps in a schedule to ensure that each tap is checked at least once per annum.

  • Blow down where possible to remove sediment and sludge

Half Yearly Checks

Heat Exchangers

  • Examine and clean strainers

Calorifiers

  • Note hot water storage temperature and log. Adjust as necessary to achieve temperature of 60ºC.

  • Check setting of each thermostat (where fitted). Re-adjust/recalibrate where required and log

  • Check all valves and draincocks for correct operation and report any defects immediately.

  • Check operation of HWS primary controls, where fitted, re-adjust where necessary

  • Check manhole cover, bolt head and access covers for correct fit an any signs of leakage and nip up as necessary

  • Check and log water temperatures at 25% taps in a schedule to ensure that each tap is checked at least once per annum.

  • Blow down where possible to remove sediment and sludge

  • Test safety devices.

  • Test thermostatic controls. Maintain storage at 60º.

  • Examine mountings, connections and thermal insulation

  • Clean and examine thermometers and altitude gauges

  • Examine vent pipes, ensure that are clear

Annual Checks

Heat Exchanger

  • Examine and clean strainers

  • Test safety valve

  • Test thermostatic controls

  • Check all valves and drain cocks for correct operation

  • Examine vent pipes; ensure they are clear

  • Clean and examine thermometers and altitude gauges

  • Drain heat exchangers and open up for inspection, removing all scale or deposits

  • Reinstate and test for correct operation

Calorifiers

  • Note hot water storage temperature and log. Adjust as necessary to achieve temperature of 60ºC.

  • Check setting of each thermostat (where fitted). Re-adjust/recalibrate where required and log

  • Check all valves and draincocks for correct operation and report any defects immediately

  • Check operation of HWS primary controls, where fitted, re-adjust where necessary

  • Check manhole cover, bolt head and access covers for correct fit an any signs of leakage and nip up as necessary.

  • Check and log water temperatures at 25% taps in a schedule to ensure that each tap is checked at least once per annum.

  • Blow down where possible to remove sediment and sludge

  • Test safety devices.

  • Test thermostatic controls. Maintain storage at 60º.

  • Examine mountings, connections and thermal insulation

  • Clean and examine thermometers and altitude gauges.

  • Examine vent pipes, ensure that are clear

  • Prepare for Engineers Survey Inspection as follows: (if required by client)

  • Isolate primary pipework on secondary pipework to calorifier.

  • Drain down calorifier secondary shell and remove bolted head or manhole cover for inspection.

  • Disconnect primary pipework to primary coil and withdraw coil for inspection

  • Clean primary coil and after inspection test to one and half times working pressures.

  • Clean inside of calorifier shell and remove all scale or deposits.

  • Refit bolted head, manhole and primary coil using new jointing rings.

  • Reconnect all pipework to calorifier and refill.

  • Ensure that the calorifier is on line and re-commission to working temperature.

  • Clean and disinfect system in accordance with BS6700 in conjunction with disinfection of CWS.

Coments

Warning Notices

  • Were any warning notices given?

  • Details of warning given

Engineer Report and Comments

  • Engineers Report or Comments

Further Works

  • Are further works or remedial actions required following this visit.

  • No further actions or remedial works required

  • The following further actions should be considered for the equipment serviced

  • Further Actions Required
  • Action

Sign Off

Location Representative Declaration

  • Please tick the following statements as conformation of completed works.

  • I confirm that the service as noted in this report was carried out

  • All immediate and further actions have been fully explained and detailed

  • If applicable, any warning notices issued have been fully explained

  • Client Signature

Elite Services Declaration

  • Please tick the following boxes as conformation of completed works

  • All site maintenance tasks completed

  • Site left clear and free of hazards

  • All equipment left operational and tested

  • All permits completed

  • Works discussed and agreed with site representative

  • Elite Environmental Services

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.