Title Page
-
Project Name
-
Location
-
Prepared by
-
Conducted on
Commissioning Checklist
HVAC System
Installation
Cabinet and General Installation
-
Permanent labels affixed, including for fans
-
Casing condition good: no dents, leaks, door gaskets installed
-
Access doors close tightly - no leaks
-
Boot between duct and unit tight and in good condition
-
Vibration isolation equipment installed & released from shipping locks
-
Maintenance access acceptable for unit and components
-
Sound attenuation installed
-
Thermal insulation properly installed and according to specification
-
Instrumentation installed according to specification (thermometers, pressure gages, flow meters, etc.)
-
Clean up of equipment completed per contract documents
-
Filters installed and replacement type and efficiency permanently affixed
Piping and Coils
-
No leaking apparent around refrigerant fittings
-
All coils are clean and fins are in good condition
-
All condensate drain pans clean and slope to drain per spec
-
OSAT, MAT, SAT, RAT sensors properly located and secure (related OSAT sensor shielded)
-
Sensors calibrated
-
If split system, refrigerant piping in good condition and suction insulated
-
P/T plugs and isolation valves installed per drawings
Fans and Dampers
-
Supply fan and motor alignment appear correct
-
Supply fan belt tension & condition good
-
Supply fan protective shrouds for belts in place and secure
-
Supply fan area clean
-
Supply fan and motor properly lubricated
-
Return/exhaust fan and motor aligned
-
Return/exhaust fan belt tension & condition good
-
Return/exhaust fan protective shrouds for belts in place and secure
-
Return/exhaust fan area clean
-
Return/exhaust fan and motor lube lines installed and lubed
-
Filters installed and replacement type and efficiency permanently affixed--construction filters removed
-
Filter pressure differential measuring device installed and functional (magnahelic, inclined manometer, etc.)
-
All dampers close tightly
-
All damper linkages have minimum play
-
Motors: premium efficiency verified, if specified?
Compressor and Condenser
-
Refrigerant sight glass clear of bubbles (if OSAT > 70F)
-
Moisture indicator shows no moisture
-
Correct oil level (check site glass during operation)
-
Compressors and piping were leak tested, as required
-
Crankcase heater on when unit is off
-
Condenser coils clean and in good condition (air cooled)
-
Adequate clearance for airflow around condenser
-
Ducts (preliminary check)
-
Duct joint sealant properly installed
-
No apparent severe duct restrictions
-
Turning vanes in square elbows as per drawings
-
OSA intakes located away from pollutant sources & exhaust outlets
-
Pressure leakage tests completed
-
Branch duct control dampers operable
-
Balancing dampers installed as per drawings and TAB’s site visit
Electrical and Controls
-
Power disconnects in place and labeled
-
All electric connections tight
-
Proper grounding installed for components and unit
-
Safeties in place and operable
-
Current overload heaters installed and correct size
-
Auxiliary heaters installed
-
Sensors calibrated
-
All building control system interlocks hooked up with packaged controls and functional
-
Enthalpy control and sensor properly installed (if applicable)
-
Related thermostats are installed
-
Related building automation system points are installed
-
All control devices and wiring complete
Testing, Adjusting and Balancing (TAB)
-
Installation of system and balancing devices will allow balancing to be done per specified NEBB or AABC procedures & contract docs
-
Safeties installed and safe operating ranges are established
-
If unit is started and will be running during construction: have quality filters on RA grills, etc. to minimize dirt in the ductwork and coils and in any finished areas. Verify moisture migration is not a problem due to improper pressures between spaces.
Operation
-
Supply fan rotation correct
-
Return / exhaust fan rotation correct
-
No unusual noise or vibration in supply and exhaust fans
-
Condenser fan rotation correct (air cooled)
-
Condenser fan acceptable noise and vibration (air cooled)
-
Measure line to line voltage imbalance for 1/3 of the compressors: Compressor 1 Phase: (%Imbalance = 100 x (avg. - lowest) / avg.) Record all three-phase voltages. Imbalance less than 2%?
-
Compressor 2 Phase: (%Imbalance = 100 x (avg. - lowest) / avg.) Record all three-phase voltages. Imbalance less than 2%?
-
Record full load running amps for each compressor. Running less than max?
-
Record full load running amps for each condenser fan. Running less than max?
-
Fans > 5 hp Phase Checks: (% imbalance = 100 x (avg. - lowest) / avg.) Imbalance less than 2%?
-
Inlet vanes aligned in housing, actuator spanned, modulate smoothly and proportional to input signal and EMS readout.
-
All dampers (OSA, RA, EA, etc.) stroke fully without binding and spans calibrated and BAS reading site verified
-
Valves stroke fully and easily and spanning is calibrated
-
Valves verified to not be leaking through coils when closed at normal operating pressure
-
The HOA switch properly activates and deactivates the unit
-
Safeties installed and safe operating ranges for this equipment provided to the commissioning agent
-
Specified sequences of operation and operating schedules have been implemented with all variations documented
-
Specified point-to-point checks have been completed and documentation record submitted for this system
Pumping System
Installation
General Installation
-
Label permanently affixed
-
Pumps installed in place and properly grouted, bases filled
-
Vibration isolation devices installed and functional
-
Factory alignment checked and appears correct
-
Field alignment, if required, completed
-
Seismic anchoring installed
-
Temperature and pressure gauges and sensors installed
-
Pump and motor lubricated
-
Pipe fittings completed and piping properly supported
-
No leaks in pipe fittings and accessories at pump
-
Piping and pump properly insulated
-
Strainers in place and cleaned out
-
Piping system properly flushed
-
Valves properly tagged
Electrical and Controls
-
Disconnect switches in place and labeled
-
Electrical connections tight
-
Proper grounding installed for components and unit
-
Motor overloads calibrated
-
Control system interlocks hooked up and functional
-
Control devices, tubing and wiring complete
VFD
-
VFD powered up and wired to controlled equipment
-
VFD interlocked to control system
-
Pressure or other controlling sensor properly located and per drawings and calibrated
-
Controller location not subject to excessive temperatures
-
Controller location not subject to excessive moisture or dirt
-
Controller size matches motor size
-
Internal settings designating the application are correct
-
Input of motor FLA represents 105% to 115% of motor FLA rating
-
Appropriate Volts vs Hz curve is being used; energy saver on?
-
Accel and decel times are around 10-50 seconds, except for special applications.
-
Upper frequency limit set at 100%, unless explained otherwise
-
Unit is programmed with written programming record available
-
VFD kW demand at panel matches BAS readout
Testing, Adjusting and Balancing (TAB)
-
Installation of system and balancing devices will allow balancing to be done per specified NEBB or AABC procedures & contract docs
Operation
-
The HOA switch properly activates and deactivates the unit under manual and automatic control.
-
Pump rotation verified correct
-
No unusual noise or vibration
-
No leaking apparent around fittings
-
Measure line to line voltage phase imbalance for each pump: (%lmbalance = 100 x (avg. - lowest) / avg.) Record imbalance of each pump. Imbalance less than 2%?
-
Record full load running amps for each pump. FL amps x factor (Max amps). Running less than max?
-
Specified sequences of operation and operating schedules have been implemented with variations documented
-
Specified point-to-point checks have been completed and documentation record submitted for this system
Piping System
Installation
Piping
-
Pipe fittings complete and pipes properly supported allowing for thermal expansion and contraction and building expansion joints.
-
Pipe joints properly installed
-
Required seismic anchoring installed
-
Pipes properly labeled
-
Pipes properly insulated
-
Piping properly sloped
-
Proper construction isolation
-
Strainers in place and clean
-
Isolation valves and balancing valves installed
-
Test ports (P/T) installed near all control sensors and as per spec
-
Piping system properly flushed and cleaned and temporary piping removed
-
10% of strainers and Owner-selected low-point drains opened and witnessed by Owner to be clean.
-
Piping hydrostatic pressure test completed according to contract documents
-
No leaking apparent around fittings
-
ASME pressure vessel data sheet or certification tag posted and inspection complete for each expansion tank and storage tank
-
Expansion tanks verified to not be air bound and system completely full of water. System purged of air.
-
Air vents and bleeds at high points of systems functional
-
Water hammer arrestors installed and tested
-
Backflow preventer proper location
-
Adequate depth of bury for service piping
-
Cross connection protection
Valves
-
Valve tags permanently affixed
-
Valves installed in proper direction
-
Pressure reducing valves set at proper pressure
-
No leaks
-
Flexible connections at equipment installed
-
Dielectric fittings for dissimilar metals installed
-
Vibration Isolation installed
-
Fire-rated pipe penetrations installed properly
-
Valves that require a positive shut-off are verified to not be leaking when closed at normal operating pressure.
Sensors and Gages
-
Temperature, pressure and flow gages and sensors installed.
Testing, Adjusting and Balancing (TAB)
-
Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents
Lighting System and Controls
Installation
Lighting Fixtures and Switches
-
Light switches are located per plans
-
Light switches are labeled with proper ID to match drawings or field changes
-
Light switch is controlling the fixtures in the area indicated on design drawings
-
Fixtures are properly supported for seismic zone
-
Verify proper lamp type is installed in each fixture to match fixture schedule and specifications
Lighting Controls
-
Lighting control is installed per manufacturer recommendations
-
Lighting control is calibrated per manufacturer checklist
Completion
-
Additional Comments
-
Inspector Name & Signature
-
Installer Name & Signature
-
Contractor Name & Signature