Title Page

  • Project Name

  • Location
  • Prepared by

  • Conducted on

Commissioning Checklist

HVAC System

Installation

Cabinet and General Installation

  • Permanent labels affixed, including for fans

  • Casing condition good: no dents, leaks, door gaskets installed

  • Access doors close tightly - no leaks

  • Boot between duct and unit tight and in good condition

  • Vibration isolation equipment installed & released from shipping locks

  • Maintenance access acceptable for unit and components

  • Sound attenuation installed

  • Thermal insulation properly installed and according to specification

  • Instrumentation installed according to specification (thermometers, pressure gages, flow meters, etc.)

  • Clean up of equipment completed per contract documents

  • Filters installed and replacement type and efficiency permanently affixed

Piping and Coils

  • No leaking apparent around refrigerant fittings

  • All coils are clean and fins are in good condition

  • All condensate drain pans clean and slope to drain per spec

  • OSAT, MAT, SAT, RAT sensors properly located and secure (related OSAT sensor shielded)

  • Sensors calibrated

  • If split system, refrigerant piping in good condition and suction insulated

  • P/T plugs and isolation valves installed per drawings

Fans and Dampers

  • Supply fan and motor alignment appear correct

  • Supply fan belt tension & condition good

  • Supply fan protective shrouds for belts in place and secure

  • Supply fan area clean

  • Supply fan and motor properly lubricated

  • Return/exhaust fan and motor aligned

  • Return/exhaust fan belt tension & condition good

  • Return/exhaust fan protective shrouds for belts in place and secure

  • Return/exhaust fan area clean

  • Return/exhaust fan and motor lube lines installed and lubed

  • Filters installed and replacement type and efficiency permanently affixed--construction filters removed

  • Filter pressure differential measuring device installed and functional (magnahelic, inclined manometer, etc.)

  • All dampers close tightly

  • All damper linkages have minimum play

  • Motors: premium efficiency verified, if specified?

Compressor and Condenser

  • Refrigerant sight glass clear of bubbles (if OSAT > 70F)

  • Moisture indicator shows no moisture

  • Correct oil level (check site glass during operation)

  • Compressors and piping were leak tested, as required

  • Crankcase heater on when unit is off

  • Condenser coils clean and in good condition (air cooled)

  • Adequate clearance for airflow around condenser

  • Ducts (preliminary check)

  • Duct joint sealant properly installed

  • No apparent severe duct restrictions

  • Turning vanes in square elbows as per drawings

  • OSA intakes located away from pollutant sources & exhaust outlets

  • Pressure leakage tests completed

  • Branch duct control dampers operable

  • Balancing dampers installed as per drawings and TAB’s site visit

Electrical and Controls

  • Power disconnects in place and labeled

  • All electric connections tight

  • Proper grounding installed for components and unit

  • Safeties in place and operable

  • Current overload heaters installed and correct size

  • Auxiliary heaters installed

  • Sensors calibrated

  • All building control system interlocks hooked up with packaged controls and functional

  • Enthalpy control and sensor properly installed (if applicable)

  • Related thermostats are installed

  • Related building automation system points are installed

  • All control devices and wiring complete

Testing, Adjusting and Balancing (TAB)

  • Installation of system and balancing devices will allow balancing to be done per specified NEBB or AABC procedures & contract docs

  • Safeties installed and safe operating ranges are established

  • If unit is started and will be running during construction: have quality filters on RA grills, etc. to minimize dirt in the ductwork and coils and in any finished areas. Verify moisture migration is not a problem due to improper pressures between spaces.

Operation

  • Supply fan rotation correct

  • Return / exhaust fan rotation correct

  • No unusual noise or vibration in supply and exhaust fans

  • Condenser fan rotation correct (air cooled)

  • Condenser fan acceptable noise and vibration (air cooled)

  • Measure line to line voltage imbalance for 1/3 of the compressors: Compressor 1 Phase: (%Imbalance = 100 x (avg. - lowest) / avg.) Record all three-phase voltages. Imbalance less than 2%?

  • Compressor 2 Phase: (%Imbalance = 100 x (avg. - lowest) / avg.) Record all three-phase voltages. Imbalance less than 2%?

  • Record full load running amps for each compressor. Running less than max?

  • Record full load running amps for each condenser fan. Running less than max?

  • Fans > 5 hp Phase Checks: (% imbalance = 100 x (avg. - lowest) / avg.) Imbalance less than 2%?

  • Inlet vanes aligned in housing, actuator spanned, modulate smoothly and proportional to input signal and EMS readout.

  • All dampers (OSA, RA, EA, etc.) stroke fully without binding and spans calibrated and BAS reading site verified

  • Valves stroke fully and easily and spanning is calibrated

  • Valves verified to not be leaking through coils when closed at normal operating pressure

  • The HOA switch properly activates and deactivates the unit

  • Safeties installed and safe operating ranges for this equipment provided to the commissioning agent

  • Specified sequences of operation and operating schedules have been implemented with all variations documented

  • Specified point-to-point checks have been completed and documentation record submitted for this system

Pumping System

Installation

General Installation

  • Label permanently affixed

  • Pumps installed in place and properly grouted, bases filled

  • Vibration isolation devices installed and functional

  • Factory alignment checked and appears correct

  • Field alignment, if required, completed

  • Seismic anchoring installed

  • Temperature and pressure gauges and sensors installed

  • Pump and motor lubricated

  • Pipe fittings completed and piping properly supported

  • No leaks in pipe fittings and accessories at pump

  • Piping and pump properly insulated

  • Strainers in place and cleaned out

  • Piping system properly flushed

  • Valves properly tagged

Electrical and Controls

  • Disconnect switches in place and labeled

  • Electrical connections tight

  • Proper grounding installed for components and unit

  • Motor overloads calibrated

  • Control system interlocks hooked up and functional

  • Control devices, tubing and wiring complete

VFD

  • VFD powered up and wired to controlled equipment

  • VFD interlocked to control system

  • Pressure or other controlling sensor properly located and per drawings and calibrated

  • Controller location not subject to excessive temperatures

  • Controller location not subject to excessive moisture or dirt

  • Controller size matches motor size

  • Internal settings designating the application are correct

  • Input of motor FLA represents 105% to 115% of motor FLA rating

  • Appropriate Volts vs Hz curve is being used; energy saver on?

  • Accel and decel times are around 10-50 seconds, except for special applications.

  • Upper frequency limit set at 100%, unless explained otherwise

  • Unit is programmed with written programming record available

  • VFD kW demand at panel matches BAS readout

Testing, Adjusting and Balancing (TAB)

  • Installation of system and balancing devices will allow balancing to be done per specified NEBB or AABC procedures & contract docs

Operation

  • The HOA switch properly activates and deactivates the unit under manual and automatic control.

  • Pump rotation verified correct

  • No unusual noise or vibration

  • No leaking apparent around fittings

  • Measure line to line voltage phase imbalance for each pump: (%lmbalance = 100 x (avg. - lowest) / avg.) Record imbalance of each pump. Imbalance less than 2%?

  • Record full load running amps for each pump. FL amps x factor (Max amps). Running less than max?

  • Specified sequences of operation and operating schedules have been implemented with variations documented

  • Specified point-to-point checks have been completed and documentation record submitted for this system

Piping System

Installation

Piping

  • Pipe fittings complete and pipes properly supported allowing for thermal expansion and contraction and building expansion joints.

  • Pipe joints properly installed

  • Required seismic anchoring installed

  • Pipes properly labeled

  • Pipes properly insulated

  • Piping properly sloped

  • Proper construction isolation

  • Strainers in place and clean

  • Isolation valves and balancing valves installed

  • Test ports (P/T) installed near all control sensors and as per spec

  • Piping system properly flushed and cleaned and temporary piping removed

  • 10% of strainers and Owner-selected low-point drains opened and witnessed by Owner to be clean.

  • Piping hydrostatic pressure test completed according to contract documents

  • No leaking apparent around fittings

  • ASME pressure vessel data sheet or certification tag posted and inspection complete for each expansion tank and storage tank

  • Expansion tanks verified to not be air bound and system completely full of water. System purged of air.

  • Air vents and bleeds at high points of systems functional

  • Water hammer arrestors installed and tested

  • Backflow preventer proper location

  • Adequate depth of bury for service piping

  • Cross connection protection

Valves

  • Valve tags permanently affixed

  • Valves installed in proper direction

  • Pressure reducing valves set at proper pressure

  • No leaks

  • Flexible connections at equipment installed

  • Dielectric fittings for dissimilar metals installed

  • Vibration Isolation installed

  • Fire-rated pipe penetrations installed properly

  • Valves that require a positive shut-off are verified to not be leaking when closed at normal operating pressure.

Sensors and Gages

  • Temperature, pressure and flow gages and sensors installed.

Testing, Adjusting and Balancing (TAB)

  • Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents

Lighting System and Controls

Installation

Lighting Fixtures and Switches

  • Light switches are located per plans

  • Light switches are labeled with proper ID to match drawings or field changes

  • Light switch is controlling the fixtures in the area indicated on design drawings

  • Fixtures are properly supported for seismic zone

  • Verify proper lamp type is installed in each fixture to match fixture schedule and specifications

Lighting Controls

  • Lighting control is installed per manufacturer recommendations

  • Lighting control is calibrated per manufacturer checklist

Completion

  • Additional Comments

  • Inspector Name & Signature

  • Installer Name & Signature

  • Contractor Name & Signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.