Audit Title
-
Client/Location
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Executive Summary
-
Executive Summary
Part 1 - Documentation
-
Is a Site Log Book available?
-
Has the Site Log Book been signed for?
-
Is there an HS&E Policy Statement on display?
-
When was the HS&E Policy Statement signed?
-
Are the current Insurance Certificates on display?
-
Is an H&S Law Poster displayed?
-
Are the correct details shown on the H&S Law Poster?
-
Is the NG Bailey QA statement displayed?
-
Is the NG Bailey Assurance Policy displayed?
-
Is the NG Bailey Drugs & Alcohol Policy displayed?
-
Have all staff signed the Record of Understanding & Compliance forms?
-
Is a 'Random Un-announced Testing List' maintained?
-
Is the NG Bailey Fatigue Policy displayed?
-
Is the NG Bailey Refusal to Work Policy displayed?
-
Have all Engineering staff undergone DZEP training?
-
Are RPOS training records available?
-
Are Task Supervisor training records available?
Part 1a - SHEQ-related Documentation
-
Are SHEQ Induction records available?
-
Are Station Induction Records available?
-
Is the Station Fire Risk Assessment available?
-
Have StationEmergency Plan Acknowledgement forms been completed?
-
Are site-specific Risk Assessment available?
-
Has training in the completion of Risk Assessments been undertaken?
-
Are Close Call/Near Miss reports being submitted?
-
Are Toolbox Talks being carried out?
-
Are Safety Talks Attendance Sheets being completed to record attendance at Toolbox Talks?
-
Are Accident Reports being completed where necessary?
-
Is a site-specific Environmental Impacts & Aspects Assessment available?
-
Are lamp coffins being managed as required?
-
Is the build up of waste, NG Bailey-controlled areas, being managed?
-
Are waste hazardous substances being disposed of safely?
-
Is waste transfer documentation held on file?
-
Has Part E been completed on the Consignment Notes on file?
-
Is an F-Gas Register in use?
-
Are copies of F-Gas Engineers' competency certificates held on file?
Part 2 - Welfare Facilities
-
Are welfare facilities provided for Engineering staff?
-
Are welfare facilities provided for office staff?
-
Are suitable changing facilities provided?
-
Are secure lockers provided?
-
Are shower facilities available?
-
Are changing and shower facilities being kept clean and tidy?
Part 3 - Work Activities
-
Is there a signing in procedure for staff and visitors?
-
Are platform edge/OHLE proximity rules being adhered to?
-
Are Engineers able to undertake their work activities without the need to work at height?
-
Have working at height issues been identified and addressed?
-
Is a ladder inspection process in place?
-
Is portable electrical equipment tested as necessary?
-
Have ear protection zones been identified?
-
Is suitable ear protection issued to all Engineers?
-
Is there a need for manual handling as part of routine work activities?
-
Has suitable manual handling instruction been provided?
-
Is an inventory of hazardous substances available?
-
Is all necessary COSHH-related documentation in place?
-
Are slip, trip and fall issues being addressed?
-
Are lighting levels suitable for the work activities being undertaken?
-
Is ventilation adequate in any enclosed areas?
-
Is First Aid cover available at all times?
Part 4 - Contract Administration
-
Are documented weekly site inspections being carried by a Supervisor?
-
Are documented monthly Safety Tours being carried out by the Contract Manager?
-
Are PPM audits carried out?
-
Are sub-contractors subject to the NG Bailey pre-selection process?
-
Are sub-contractors RAMS being reviewed by the Supervisor/Manager?
-
Are Permits to Work issued to all sub-contractors prior to work commencing?
-
Are all Permits to Work being completed correctly?
-
Are sub-contractor audits carried out?
-
Are customer complaints/non-conforming product investigated and reported upon?
Part 5 - Resource Management
-
Are Job Descriptions in place for all contract employees?
-
Have all job-specific competencies been identified?
-
Is a training matrix maintained?
-
Is there a planned programme for periodic staff performance reviews?
-
Where job-specific competencies are needed, has the training been provided?
-
Are HS1-specific competency requirements being addressed?
-
Are NGB Rail inductions carried out?
-
Is RPOS AND TS development planning in place?
-
Does equipment being used conform to the laid down standards (C/07/OS/09/1600 'Product Acceptance')?
-
Are there any records to show material supplies conform to the required standard?
-
Are sub-contractor performance and response times being monitored?
-
Are SHEQ reports reviewed and the necessary actions implemented to address issues noted?
-
Are management reviews of contract performance carried out?