Inspection Information
-
Project Name:
-
Project Location
-
Permit #
-
Hood System Vendor and Contact Information
-
Date of Inspection
Visual Inspection
Appliances
-
Appliances located within the perimeter of the hood, minimum of 6 inches
-
Appliances on casters
-
Caster channels installed or an alternative means to ensure appliances are returned to design position
-
Chain / cable that is shorter than the gas lines secured to the wall and to the appliances
-
Quick connect fittings are correctly installed with the flow of gas (check arrows)
-
Deep fat fryers are a minimum of 16 inches away from an open flame -or- an 8 inch steel or tempered glass baffle is installed
-
Appliances are of the same size and type as shown on approved plans
-
Hood and exhaust ducts are the same size as shown on approved plans
Nozzles
-
Nozzles are the correct type as shown on the approved plans
-
Nozzles are the correct distance above the cooking surface (see drawings / spec sheets):
-
Nozzles are correctly aimed using the laser (see spec sheets for proper aiming point):
Fusible Links
-
Fusible links positioned as shown on approved plans:
-
Fusible links proper temperature as indicated on approved plans:
Manual Pull Station
-
Pull station located 10 - 20 feet from the protected hood and in the path of egress:
Type K Fire Extinguisher
-
Type K fire extinguisher located 10 - 30 feet from the protected hood:
-
Sign posted over extinguisher stating to use hood system before extinguisher:
Visual Inspection Status (Add notes explaining reasons for failure)
-
Visual Inspection Status:
Operational Test
Manual Activation (Pull Station)
-
System tripped
-
Make-up air shut off
-
Exhaust fan stayed on
-
Gas feed shut off and had to be manually reset
-
Electrical tripped to all appliances under hood
-
Alarm activated / monitoring if applicable
Automatic Activation (Fusible Link)
-
System tripped
-
Make-up air shut off
-
Exhaust fan stayed on
-
Gas feed shut off and had to be manually reset
-
Electrical tripped to all appliances under hood
-
Alarm activated / monitoring if applicable
Operational Test Status
-
Operational Test Status:
Inspection Status
Additional Comments
-
Comments:
Inspection Status Summary
-
Visual Inspection:
-
First Operational Test:
-
Second Operational Test
-
Third Operational Test
Signatures
-
Fire Protection Contractor Name
-
Fire Protection Contractor Signature
-
Estes Valley Fire Inspector Name
-
Estes Valley Fire Inspector Signature