Title Page
-
Conducted on
-
Prepared by
Inspection Details
-
Project Name
-
Manager
-
Client
-
Date
-
Area Inspected
Installation
-
1. Correct fixings used 5.5x150/175mm - install to SFS
-
2. Correct fixing used CSF 180mm - install to Concrete
-
3. Fixing the Ancon Channel thorough small holes (5,3mm) into Steel or Timber
-
4. Fixing the Ancon Channel thorough large holes (9.5mm) using CFS Screws into Concrete
-
5. CFS Fixings used in combination with Ancon Compression Sleeves – same length as the insulation
-
6. Concrete fixing – minimum embedment 50mm, min. hole depth 60mm<br>A small impact driver to be used - 150Nm torque
-
7. Vertical screw spacing 225mm
-
12. Work area left clean and tidy
-
Insulation installed with the patterned side facing outwards
-
Insulation staggered in accordance with good fixing practice
-
Joints closely butted to optimise the insulation performance
-
Insulation tightly fitted around wall brackets where these occur
-
Insulation fixed using the manufacturer typical fixing pattern and 1no stainless steel fixing with washer fixed on the centre of each insulation slab
Sign Off
-
JC Drylining Ltd Signature
-
Main Contractor Signature
COMMENTS
-
JC Drylining Ltd comments
-
Main Contractor returned comments