Title Page

  • Conducted on

  • Prepared by

Inspection Details

  • Project Name

  • Manager

  • Client

  • Date

  • Area Inspected

Plasterboard - prep

  • 1. Surface is clean, dry and suitable to receive Plaster

  • 2. All plasterboard joints, scrim taped

  • 3. Wall and ceiling intersections, scrim taped

Conditions

  • 4. All surfaces reasonably dry and protected from weather

Plastering - Application

  • 5. If applicable, movement joints installed corresponding with joints in background

  • 6. Angle beads / corner tape fitted plumb and square

  • 7. Angle bead, edge bead and stop bead / corner tape - mitres correct

  • 8. Skim coat applied

  • 9. All electrical boxes cleaned out

  • 10. Skirting line cleaned without snots

  • 11. Work area left clean and tidy

De-snag / Making Good

  • 12. Plastering imperfections highlighted, filled and rubbed down

  • 13. Work area left clean and tidy

Sign Off

  • JC Drylining Ltd Signature

  • Main Contractor Signature

COMMENTS

  • JC Drylining Ltd comments

  • Main Contractor returned comments

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.