Title Page
-
Conducted on
-
Prepared by
-
Location
-
Has a risk assessment and method statement been prepared
-
Are steel stanchion bases correct for level
-
Check position and condition of holding down bolts and boxes
-
Check that bolt boxes are clear of mud, debris and water prior to grouting
-
Re-affirm erection start point/programme
-
Check top level of beams at each corner of building
-
Check steel for plumb and alignment at all corners
-
Check all cross bracing is fitted as drawings
-
Check fitting of all sag rods and sheeting rails
-
Check roof purlins and trimmings steelwork fitted
-
Check cleanliness of steelwork
-
Check for handling or erection damage to paintwork
-
Check holding down bolts and fitting of stanchion packs
-
Check on site cutting and welding is to specification
-
Check all connections are bolted and torqued as specified
-
Check for missing bolts at angled connections
-
Grout all holding down bolts as specification
-
Ensure steelwork is encased below ground and cover correct