Title Page
-
Audit Title
-
Job Description
-
Conducted on
-
Prepared by
-
Location
-
Service Provider
-
Subcontractor
-
Crew Leader
Audit Protocol for MG SWP CP3.003
6.1 – Receive Instruction to conduct Earth Electrode Measurement
-
Have instructions from the Supervisor been received to conduct the earth resistance measurement?
6.2 – Install Earth Spikes
-
Have the electrodes been inserted at the correct intervals?
6.3 – Connect Leads
-
Have the leads been connected correctly?
6.4 – Measure Resistance
-
Was the resistance measurement obtained?
6.5 – Record Results
-
Have the results been recorded?
6.6 – Submit Results to Supervisor
-
Have the results been submitted to the Supervisor?
6.7 – Finish
-
Has site been packed up and made safe?
Comment & Sign Off
-
Comments and Audit Finding Summary
-
Auditor(s)
-
Auditee (Crew Leader)