Can the work be undertaken from the ground or from a solid construction?
-
If not can the work be undertaken using a passive fall prevention device? (Tick applicable)
-
Scaffolds
-
Perimeter screens
-
Step platforms
-
Perimeter guard railing
-
Elevating work platforms
-
Guard railing edges of roofs
-
Mast climbing work platforms
-
Protection for trenching works
-
Work boxes
-
Safety mesh
-
Can the work be undertaken using a fall arrest system? Tick applicable
-
Travel restraint systems
-
Industrial rope-access systems
-
Can the work be undertaken using a fall-arrest system?
-
Safety harness systems (other than travel-resistant systems)
-
Catch platforms
-
Working at Heights (WAH) permit, SWMS / JSEA in place
-
WAH permit, SWMS / JSEA reviewed and signed by all involved in the task
-
Fall prevention equipment inspected and suitable for task
-
Fall prevention systems insatlled and inspected by a competent person
-
Personnel trained in the use of equipment
-
Tools and equipment secured by lanyards (hard hats secured by chinstraps)
-
Spotter being used for all WAH activities at all times
-
Exclusion areas (below) defined and controlled by barricading, signange and spotter
-
Wind speed is acknowledged and operations are halted during strong winds as determined by risk assessment and/or plant (EWP) manufacturer's operations manual?
-
Rescue plan in place and adequate
-
Have the following common WAH hazards been assessed?
- surfaces (slips, stability, strength and slope)
- level changes
- stability of structures (temporary or permanent)
- the ground (stability and evenness of the ground for scaffold or work platforms)
- edge protection (including protection around open edges of floors)
- openings and holes (guarding in place)
- any loads on elevated work areas above workers
- hazards below (star pickets, reo bars)
-
Signed PoMC Representative: