Information
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1. Compliance with Conditions of Consent
-
Does the plan of management relate to the on-ground work at the Quarry? Comment:
-
Areas Of Compliance
-
Add media
-
Areas Of Non Compliance
-
Add media
-
Is the quarry operating within the footprint of the approved plan? Comment
-
Add media
2. Access Tracks
-
Are the Access tracks correctly constructed - stable, all weather access? Comment
-
Add media
-
Are adequate erosion and sediment control measures in place (for access tracks)? Comment
-
Add media
-
Are the erosion and sediment controls functioning satisfactorily? Comment
-
Add media
3. Topsoil/Overburden
-
Is topsoil / overburden being stockpiled for later rehabilitation? Comment
-
Add media
-
What is approx. quantity of material stockpiled?
-
Add media
-
Is the stockpile adequate for later rehabilitation? (< @ 1 metre in height for viable seed stock, etc.)? Comment
-
Add media
-
What are the disposal measures for the overburden? if required) Comment
-
Add media
4. Sediment and Erosion Control Measures
-
Are clean water diversion drains/swales in place and functioning satisfactorily?
-
Add media
-
is there an erosion and sed plan in place Y/N
-
Add media
-
What sediment and erosion controls in place?
- Sediment Filters
- Sediment Trap
- Sediment Basins
- Sediment fences, hay bales
-
Details of sediment and erosion controls in place.
-
Add media
-
Are they functioning adequately and installed correctly (right location, size etc.)?
-
Add media
-
Is the site and batters stable? Comment.
-
Add media
5. Rehabilitation
-
What measures are in place for rehabilitation (plan etc)?
-
What is the current area that requires rehabilitation?
-
Add media
-
Approximate cost to rehabilitate site?
-
Add media
-
Details of required rehabilitation (machine usage and actual work etc)?
-
Add media
-
Is progressive rehabilitation occurring on the site (site is to be progressively rehabilitated with max. excavated areas complying with consent conditions)?
-
Add media
6. Ongoing Extraction
-
Is the current extraction area part of the original Plan of Management?
-
Add media
-
Where is the planned extraction directed over the next 12 months?
-
Add media
-
Is the planned extraction included in the Conditions of the original Development Consent?
-
Add media
7. Reports and Contributions
-
Have all annual reports been submitted on time and in accordance with the consent?
-
Add media
-
Are there outstanding annual fees or contributions payable to Copuncil in accordance with the consent?
-
Add media
-
Any other comment?
-
Add media
8. Plans of Management
-
Has a Plan of Management been done for the pit?
-
Add media
-
Any areas of Plan of Management not complied with?
-
Add media
-
Any additions required to Plan of Management?
-
Add media
-
Have operating and rehabilitation stages been noted on plans?
-
Add media
-
Are Traffic Management Plans accurate and working?
-
Add media
9. Planned Works
-
Details of any geotech work required
-
Add media
-
Approx cost of geotech work
-
Add media
-
Details of any survey work required
-
Add media
-
Approx cost of survey work
-
Add media
-
General works required and costs
-
Add media
-
Have boundaries been clearly marked?
-
Add media
Site photo
-
Add media