Information
-
Audit Title. R44 - Earthworks - Embankment (Ed5 Rev 0) .
-
Project Name: Tabulam New Bridge.
-
Location: BRUXNER HIGHWAY TABULAM
-
Contractor
-
Prepared by
-
Conducted on
Work Activity Record
-
Cl 1.6.1 Has survey set out been installed for all Embankments
Cl 2.3 REMOVAL OF TOPSOIL.
-
Are erosion and sediment controls in place prior to commencing removal of topsoil?
-
Are all working areas maintained so as to ensure run-off of water without scouring or pounding.<br>
-
Has precautionary activities (such as sealing off) been implemented to minimise ingress of water into earthworks material.
-
Has the required action been taken to minimise the generation of generation of excessive dust.
-
Has the topsoil been left in place where bridging layers are to be used.?
-
Are topsoil stockpiles in a approved location.<br>Be free of subsoil and other excavated material.<br>Height not exceeding 2 metres.<br>Batters been track rolled or stabilised. <br>Been seeded within 7 days of completion of 500m2 of exposed batter face.
-
Has the hold point been released.
-
HOLD POINT Cl 2.3.3.
Cl 2.4 UNSUITABLE MATERIAL.
-
After the stripping of topsoil covering each embankment foundation , has the contractor allowed the inspection of the foundation.?<br>Has the contractor notified of any areas of the foundation or any layer of foundation that rut excessively, yield or show signs of distress or instability.? <br>Has any areas of unsuitable material (as defined in Cl 1.4) been found, such unsuitable material must be excavated to the extent directed by the Principle.?
-
Has the Principal inspected the excavation and released the hold point.
-
HOLD POINT 2.4.1.
-
Cl 2.4.2 and Has the unsuitable material been used in the embankment fill.
-
Cl 2.4.3 Has the unsuitable material been replaced with either \<br>(a) Suitable material in accordance with clause 5.1 <br>Or<br>(b) if directed, with a foundation treatment in accordance with clause 3 or as shown on the drawings.
Cl 2.8 MATERIAL IN UPPER ZONE OF FORMATION, VERGES AND SPILL THROUGH BRIDGE ABUTMENTS.
-
Cl 2.8.2 Is the material used for Upper Zone Material, verge material and spill through abutment fill material being obtained from the borrow area. . <br>
-
Cl 2.8.4
-
Does the fill material conform to clause 2.8.7.<br>)<br>Free of stone larger than 53 mm. <br>no less than 50% passing the 19mm sieve.<br> <br>Was the material stockpiled, sampled and tested in accordance with Cl 2.8.3.
-
Cl 2.8.7 Earth fill at spill through bridge abutments:
CBR min 8 (10Day),PI min 5 max 8 (R44 A2.2) -
Cl 3.2 Has the hold point been released.
-
Cl 3.2 Foundation Treatments.
-
Cl 3.2 Have further treatments been ordered.<br>Have these treatments been completed. <br>Material replacing unsuitable under embankments and foundation treatments for embankments (except E2 bridging layer and Type E5 drainage layer) CV 95
-
Cl 3.3 Is the embankment on a hillside if so:<br>Has terracing been carried out as per this clause.
-
CL 5.1.2 Materials for embankment construction must be :<br>Free from tree stumps, roots and refuse.<br>Must be obtained from within the site or borrow pit. (Unless authorised by the principal) <br>Programme and manage the works as detailed in the Earthworks plan.
Cl 5 EMBANKMENTS
-
Cl 5.1.3, 5.2.1, 5.2.2 <br>Embankment Construction the material to be placed:<br>In layers parallel to the grade line.<br>Compacted to achieve relative compaction over the full depth of the layer.<br>
-
Cl 5.2.1 The particle size limitations and proportion of rock in earth fill material must be in accordance with
-
Cl 5.2.2 Layers (after compaction) must be not less than 100mm or more than given in table R44.5
-
Cl 5.2.3 Earth Fill at Spill Through Bridge Abutments.
-
Cl 5.2.3 Is the zone the correct dimensions. Is the material being placed in Max 300mm layers when compacted.
-
Do the finished batters conform to the tolerences in table R44.8
-
Cl 5.6.2. Is the material being placed adjacent retaining walls and bridge abutments of the type and to the extent in accordance with spec RMS B30. <br>
-
Cl 5.6.3 is the material being placed adjacent to culverts and other drainage structures of the type and to the extent in accordance with spec RMS R11<br>
-
Has the Principal released the hold point.
-
Cl 6.1.1 HOLD POINT
-
Cl 6.1.1 Before placing any imported Upper Zone Material:<br>Carry out a survey to determine the surface levels at sufficient locations to latter determine the volume of compacted imported material placed in the works.
7 ADDITIONAL CONFORMITY REQUIREMENTS
-
Cl 7.1 Has the layer been trimmed prior to and during compaction.
-
Cl 7.2 Is the moisture content within the range specified.<br>Annexure R44/A5 Moisture Range 60-90%.
-
Cl 7.3.2 Is the lot homogeneous.
-
Cl 7.3.4 Is only a single test method being used for the lot.
-
Cl 7.3.7 Are test holes being repaired as detailed in the contractors Project Quality Plan.
-
Has the layer been compacted to the required limits Table R44.10 CV 98%<br>Has the surface been trimmed to required tolerance Table R44.11 +0mm/-40mm
-
Cl 7.4 Has the layer been compacted to the required limits:
-
Has the proof roll been requested by the contractor and was the proof roll witnessed.
-
Cl 7.6.1 Proof Rolling Witness point.
-
Has the contractor notified of the time, date and location of the benkelman beam testing and results of proof rolling. <br>Was the testing witnessed.
-
Cl 7.6.2 WITNESS POINT Process to be witnessed: Benkelman beam testing of the underside of SMZ
-
Cl 7.6.2 Benkelman Beam Witness point (if applicable)
-
Cl 7.6.2 Was the testing Witnessed.
-
Cl 7.6.2 Benkelman Beam. HOLD POINT. (If applicable)
-
Cl Has the HOLD POINT been released.
G22 Safety and G36 Environmental
G22 SAFETY
-
Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>
-
Has a SWMS been developed.
-
Is each and every item of plant being used for its designated and intended purposes.
-
Have the attachments for plant and processes been approved and used in accordance with their design and purposes.
-
Is the correct PPE being worn
-
Were any unsafe practices observed. <br>
-
Safe work practices observed.
G36 ENVIRONMENTAL
-
R44 Cl 1.7 Were erosion and sediment controls in place prior to the removal of any topsoil.
-
Are Erosion and Sediment controls measures being installed and maintained.
-
Has mud been prevented from being deposited on roadways.
-
Have any environmental incidents or potential incidents been observed.
-
Good environmental procedures observed.
Compliance and Follow-up action.
-
Is the activity compliant.
-
NCPN or memo number.
-
Surveillance Officer
-
Follow up action
-
Product Non Conformance
-
System Non Conformance
-
Contractor generated NCR
-
Contractor generated a CAR
Matters arising
-
NCPN no
-
Contractors NCR no
-
CAR no
-
Closed out.
-
RMS representative's name