Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site Office/Desktop Inspection
-
Has the PM/PE completed the Initial Project Quality Setup form.<br>- This is currently under development and will form part of the Project Quality Pack when completed.
-
Is the Quality Plan located within the site office, and has it been signed by the Project Manager?
-
Is a copy of the Quality Policy clearly displayed within the site office?
-
Is a copy of the contract located on site?
-
Is a copy of the relevant specifications located on site?
-
Are the drawings available on site, and are the latest revisions?<br>(Refer to the project drawing register)
-
Is a copy of the works program displayed clearly within the site office, and is it the latest revision?
-
Are the quality testing requirements available on site. <br>- Ask: What governs the quality testing requirements for this project? (Example: Ipswich City Council specification)<br><br>Note: These can be located within P:Drive
-
Have the quality tests been carried out as specified per the project specifications and, are these accessible on site?
-
Have project inspections been carried out in accordance with the specifications and documentation is available accessible on site?<br>(Example; Does the contract say we need fortnightly meetings with the client?)
-
Have meetings with the client been carried out as requested and minutes have been recorded?
-
Have NCRs/ CAs/ PAs/ Complaints or other quality related issues been emailed to the Q.A manager?
-
If the project is within 14 days of practical completion, has practical completion been requested to the Engineer/Client?
-
If the project is behind programme and is not going to meet the contract practical completion date, have EOTs been requested and approved to cover this period?
-
Are all of the subcontractors working on site working under a Shadforths Subcontractor Agreement?
Tier 1 Projects Only
-
Work has been broken up into lots, and a lot register is maintained and accessible on site
-
ITPs have been filled out correctly and all relevant signatures obtained including milestones, witness points, hold points and authority to proceeds has been given.
Site Inspection Audit
-
Have all trenches been compacted properly?<br>* Compacted in maximum layers of 500mm<br>* Appropriate compaction equipment used<br>* Appropriate material used (material moisture content ok, material binding together (not to dry?))
-
Road Pavement<br>* Compactions adequate, moisture content ok, material suitable<br>* pavement shape ok, crown pointed not rounded
-
Asphalt / Seal<br>* No water ponding<br>* Rid-ability
-
Concrete (Footpaths / Kerb / Pram ramps, etc)<br>* No water ponding <br>* Visually good, no cracks, adequate expansion and contraction joints
-
How many Subcontractor/Supplier Performance Assessment forms (QA-05-12) have been filled in on different Subcontractor/Suppliers?
Rectification Action Plan
-
What needs to be rectified before the next audit?
-
Name of Auditor and signature