Title Page

  • Location:

  • Date:

  • Inspection by:

Untitled Page

OHS&E

  • Has Weekly OHS&E Inspection been completed?

  • Is the house clean for this scope of works to commence?

  • Comply with SWMS working from heights requirements?

  • All tools must be tagged and tested?

  • Observe UV Sunsmart requirements?

  • Suitable fall protection is in place?

  • Window/door openings and voids have a safety rail installed on first floor/

  • Have all risks been assessed?

Rough Ins

  • All plumbing rough in works have been completed including upper and lower and stacks are installed

  • All plumbing rough in works are at the correct height and side of showers etc?

  • Solar panels and gas points have been installed?

  • Shower bases are hooked up and recesses filled?

  • All electrical rough in works have been completed?

  • Exhaust fans and rangehoods have been ducted?

  • All heating and cooling units and ductwork have been completed and evaporative units installed?

  • Holes drilled through 90mm studs and plates, require holes to be drilled at a minimum distance of 270mm apart. Check plumbing and electrical rough ins.

  • Electrical wiring systems are to have a minimum of 25mm separation from any ground water pipping.

  • Plumbing and electrical cannot share the same conduit to the island bench.

Carpentry Lock up

  • Ensure carpenter lockup is complete in accordance with scope of works.

  • Lockable front and rear doors are installed with correct margins and fixing points.

  • All cavity doors are installed plumb, level and square. Hardware placed inside of cavity frame?

  • External door jambs have minimum three 75mm nails to each side and are fully packed?

  • Have the garage door noggings are installed?

  • Toilet roll holder and towel rail noggings are installed?

  • Tile underlay has been installed to all wet areas (glued and nailed)?

  • Check all celing noggings have been installed to take plaster?

  • Shower bases are installed on a mortar bed?

  • Packers are nailed every 150mm and has tapered ends?

  • All walls to be straightened to within +/- 1mm

  • Has underlay been glued down?

  • Are all nails to underlay flush with surface? ( they are not to be proud or penetrate surface.)

Re-Frame Checks

  • All ceiling battens are installed at 450mm centres and in one direction?

  • Trusses have been packed and cornice lines straightened to all long runs?

  • Ensure all parapet wall box gutters are completed and are watertight?

  • All roofing areas are complete including extension areas such as canopies?

  • Check house is watertight?

  • Manhole is framed out and marked on the floor? (600mx600mm)

General

  • Check top chords of floor joists have not been cut or checked out/

  • Smart joists do not have holes drilled in them by trades

  • It is the site managers responsibility to confirm that plaster is ready to load?

  • has the house been cleaned out and ready for the next trade?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.