OHS&E

  • Has Weekly OHS&E Inspection been completed?

  • All tools and equipment tested and tagged?

  • Suitable fall protection in place?

  • Window/door openings have a safety rail installed on first floor? (at one metre)

  • Is the void protection in place?

Pre-start

  • Has the house and garage been swept out and cleaned by each trade prior to the delivery of plasterboard?

  • Is there sufficient access for the delivery of plasterboard?

  • Remove any temporary wall bracing at the time of the frame?

Insulation

  • All insulation to walls to be completed?

  • All ceiling insulation to be completed under metal deck roofs and/or skillion roofs?

  • All fire seal/party walls are to be installed to manufacturers requirements?

General

  • Has the meter box got a cavity flashing installed above?

  • Are all cavities free from mortar build up (bricklayers should have cleaned)?

  • Has all mortar been removed from the noggings and bottom plate (bricklayers should have cleaned)?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.