Title Page
-
Site conducted
-
Inspection Date
-
Prepared by
-
Location
-
Personnel Present:
General And Site Set up
-
OHS&E management plan on site?
-
OHS&E management plan complete and up to date?
-
Emergency phone numbers and evacuation plan displayed?
-
Site supervisor has access to Acts, regulations, codes of practice?
-
UV cream, Face masks - P2 ear plugs insulated hooks and bunting available in the site office or car?
-
Evacuation assembly area allocated and posted?
-
Warning horn or other method of evacuation notification available in site office or car?
-
Emergency evacuation trial conducted? (Note: to be conducted every six months)
-
Traffic management plan in place?
-
Visitors register up to date?
-
OHS&E Noticeboard in place?
-
If you are injured poster, toolbox talk, weekly safety walk and safety posters displayed?
-
No smoking sign displayed in site office?
Employee Responsibilities
-
Has the weelky OHS&E walk been conducted, up to date and placed on OHS&E noticeboard?
-
Have toolbox talks been conducted on a regular basis and placed on notice board?
Work Areas
-
Are after hours contact name and numbers displayed in the appropriate Places?
-
Site signage displayed for every lot number?
-
Is site signage complete and correct?
-
Has barrier tape been erected and maintained to identify any unsafe areas?
-
Are all sharp objects capped or protected ie: star pickets, reo bars?
-
General housekeeping. Has all rubbish been placed in bins provided or identified areas?
-
Is house access and egress free from building materials?
Access And Egress
-
Temporary fencing in place and effective?
-
Clear access to worksite?
-
Clear access through garage to house door?
-
Crushed rock walkways provided if required?
-
Overhead electrical cable defined and protected?
-
Designated storage area for materials/equipment?
Sanitary
-
Adequate number of toilets?
-
Toilets clean?
-
Clear access to all toilets?
Personnel Protective Equipment (PPE)
-
Eye protection being worn where required?
-
Hearing protection being used where required?
-
Breathing apparatus being used?
-
UV protection being used?
-
Appropriate footwear being worn?
Safe Work Method Statements (SWMS)
-
Supervisors have access to SWMS?
-
Do trades have a copy of their SWMS on site?
-
Are trades working to their SWMS?
-
Framing Carpenter has a specific SWMS for Truss Installation?
Explosive Power Tools (EPT) and Nail guns
-
If an explosive power tool is on site, are the charges and tool protected in a locked box to prevent unauthorised access?
-
Is the EPT being used on recommended materials?
-
Verify the person operating the EPT is competent?
-
Is the operator of the EPT using safety goggles or face shield?
Environmental - Hazardous Substances and Dust/Fibres
-
Polyurethane Pods picked up and removed?
-
MDF cutting is in a ventilated, isolated area?
-
Cement fibre products, cutting is in a ventilated, isolated area?
-
Engineered stone cutting is not to take place on site?
-
Synthetic mineral fibre sealed bagged and removed?
-
Safe removal and control of asbestos?
Electrical Safety
-
Meterbox board Residual Current Device (RCD) tested and tagged every month?
-
Power tools and leads tested and tagged every three months?
-
Temporary wiring labelled as temporary?
-
Lead stands and insulated hooks used where required?
-
RCD multi plug portable outlet device used safely and appropriately?
-
Power tools and equipment protected by earth Leakage?
-
Domestic power boards, double adapters and piggyback adapters are not in use?
-
Leads exiting meterbox through designated area at bottom?
Excavation, Trenching
-
Are there any excavations currently on site? If No proceed to the next section.
-
Are excavations greater than 1.5 metres battered, benched or shielded?
-
Are excavations greater than one metre fenced off or bunting installed?
-
In ground services information available (Dial before you dig, as built plans, cable pipe locator and hand digging as required to locate services?)
-
Safe entry/exit from excavations?
-
Are all pits suitably covered?
-
Are there items of plant working closer than one metre to the open edge of the excavation, trench or batter?
Mobile Plant and Equipment
-
Is there any mobile plant or equipment operating on site? If No proceed to the next section.
-
Does all plant have flashing lights and audible reversing beeper?
-
Does all plant on site has proof of maintenance and is in good working order?
-
Verify that concrete pumps and mobile crane records are available and up to date?
-
Are out riggers fully extaended and on timber supprots?
-
Safe working loads are marked on the gear?
-
Lifting slings and chains are in good condition and maintained?
Working at Heights
-
Has the void protection been signed off and certificate provided?
-
Is the void protection in place prior to first floor flooring being installed?
-
Is the void cover down while workers are working on first floor
-
Has the guardrail been signed off and certificate provided?
-
Is guardrail in place prior to installing first floor flooring?
-
Roof guardrails in place around perimeter of all lower roof where work is being undertaken?
-
Handrails, midrails and toe boards have been installed and maintained on balconies?
-
Is there appropriate fall protection in place such as scaffolding or hung scaffolds for all work being undertaken on the second floor?
-
Are Carpenters working from ladders or scaffolding while placing the roof trusses?
-
If carpenters are working from ladders to install roof trusses does their SWMS reflect this scope of works?
-
Are all ladders secured, 1:4 vertical ratio, project 1 metre above platform?
-
Has the framer installed temporary handrails over window openings lower than one metre?
Scaffolding and Ladders
-
Is there any Scaffolding erected on site? If No proceed to the next section.
-
Is the scaffold certificate in place and signed off every 30 days? (Scafftag)
-
Sole boards must either pick up two standards or be a minimum of 450x225x32 hardwood or laminated. The scaffold must be fitted with base plates and screw jacks?
-
Handrails, midrails and toe boards have been installed and maintained?
-
Are diagonal bracing in place every 3rd bay front and rear?
-
Is scaffolding tied back into house?
-
Is there adequate clear access to the scaffold?
-
Are all transoms fitted every 2 metres and locked in, not left loose?
-
Are all ledgers fitted every 2 metres and locked in, not left loose?
-
Are all base plates sitting on the sole boards?
-
Are the wok decks fully planked out? with no missing planks or holes in the scaffold?
-
Are all gaps no greater than 225mm adjacent to the face of the structure/building?
-
Are scaffold decks clear of debris?
-
Are all platforms fully planked?
-
Are trestle scaffolds set up on even ground or adequately packed to ensure stability, and fully planked out?
-
Are all ladders commercial grade and without structural damage?
-
Can a worker use both hands to climb and descend ladder?
-
Is the platform appropriate for the Task i.e. no milk crates or similar to be used.
Hand Held Power Tools
-
Are appropriate handheld power tools being used for tasks?
-
Verify that regular inspections and maintenance of the power tool has been undertaken (this may be visual)
-
Are all power tools protected by RCD while being used?
-
Are all petrol driven power tools and/or generators being used in a well ventilated area?
-
Verify that guards are fitted and in good working order?
-
Verify that PPE is being used while operating power tools?
Hazard Substances
-
Hazardous and dangerous goods are not stored on site?
-
Are current Material Safety Data Sheets (MSDS) available for all hazardous substances on site and recorded?
-
Access to the MSDS by employees?
Environmental
-
Are waterways protected?
-
Up stands capped?
-
Silt protection required/in place?
-
Do drains have adequate cover?
System Review
-
Verify that workers know who the first aiders are on site?
-
Verify that workers have been inducted into the site safety rules?
-
Verify that workers understand the evacuation procedure on site?
-
Verify that workers have completed a toolbox talk?
-
Verify that first aid injuries are being recorded and a copy sent to the Building and OHS&E Managers.
Summary
-
Summary - Supervisor to complete summary