Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
SITE CONDITIONS
- Hot
- Dry
- Fine
- Showers
- Damp
- Wet
- Unsuitable for work
-
TRAFFIC MANAGEMENT
- good
- adequate
- more required
- not required
-
FENCING & O H &S SIGNAGE
1.0 ACTIVITY : SEWER,
-
Sewer Sub Contractor Onsite
- Adept Drainage
- Foot & Brown
- Bricker
- Canfam
- Delplant
- Fortunato group
- Fulton hogan
- Civ2con
- Helms plumbing
- R S Connell & Son
- Chad Oak
- Plumtrax Plumbing
- JHL
-
Sewer Retic Staus
- Not/Applicable to site
- Setting up on site
- Commenced work
- Progressing on site
- Near completion
- Testing of finished work required
- Works completed
- Signed off by authority
- suspended
1.2 Safety - Trenching, Pipelaying,Manholes, Backfill
-
Are trenches barricaded and made safe when left open.
-
Is lifting equipment suitable for the works being carried out.
-
Have workers on site been provided with a ladder or other means of access or egress where required
-
Are confined space entry authorised personnel on site with safety equipment
-
Are hats and vests being worn by workers where required
-
Are shields being used in trenchs
-
Do the works require confined space entry
-
Is a qualified mine manager on site during all excavations
-
Are environmental No Go areas fenced where required.
1.3 Environmental - Earthworks, Excavation.
-
Do stockpiles have adequate silt runoff protection.
1.4 Works - Trenching, Pipe-laying, Manhole building,Backfill
-
Does the contractor have current construction design with the latest revision number on site.
-
Is there an accredited pipe layer on site where required.
-
Does plant and equipment have suitable warning lights and reversing beepers
-
Are trench widths adequate for pipe size/ type.
-
Are pipes being installed as per design.
-
Type of pipe being used as per design drawings.
-
Are clearances to other services being maintained as per specification.
-
Does trench backfill material comply with standard drawings and specifications
-
Is the bedding material & thickness within tolerance and being compacted correctly
-
Is ground support suitable for the ground conditions and depth of excavation
-
Are end caps being used during construction where required.
-
Are boundary traps required on the project.
-
Have property branches been marked with PVC pipe to allow for asset recording purpose.
-
Has the concrete for manholes been placed and vibrated.
-
Is the surface finish of pit / manhole walls satisfactory.
-
Is compaction being done by contractor,and tested by registered contractor.
-
Are lids / covers as per design and correct rating.
-
Are pipes being stored on site as required.
1.4 Manhole-Inspection.
-
Have shields being used when manhole construction
-
Is form work adequate for the structure being constructed.
-
Does chase appear to be smooth and radial.
-
Do drop pipes and brackets appear to be in correct location.
-
Manhole hole / Inspection shaft located in the correct drawing design location.
-
Has construction of sewer main been within the correct easement area.
-
Step irons and Ladders spacing ok.
-
Have covers been greased at completion of works.
-
Connection to existing main been completed.
-
Have plugs been removed.
COMMENTS / PROGRESS / INSTRUCTIONS.
-
PHOTOS