Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • SITE CONDITIONS

  • TRAFFIC MANAGEMENT

  • FENCING & O H &S SIGNAGE

1.0 ACTIVITY : SEWER,

  • Sewer Sub Contractor Onsite

  • Sewer Retic Staus

1.2 Safety - Trenching, Pipelaying,Manholes, Backfill

  • Are trenches barricaded and made safe when left open.

  • Is lifting equipment suitable for the works being carried out.

  • Have workers on site been provided with a ladder or other means of access or egress where required

  • Are confined space entry authorised personnel on site with safety equipment

  • Are hats and vests being worn by workers where required

  • Are shields being used in trenchs

  • Do the works require confined space entry

  • Is a qualified mine manager on site during all excavations

  • Are environmental No Go areas fenced where required.

1.3 Environmental - Earthworks, Excavation.

  • Do stockpiles have adequate silt runoff protection.

1.4 Works - Trenching, Pipe-laying, Manhole building,Backfill

  • Does the contractor have current construction design with the latest revision number on site.

  • Is there an accredited pipe layer on site where required.

  • Does plant and equipment have suitable warning lights and reversing beepers

  • Are trench widths adequate for pipe size/ type.

  • Are pipes being installed as per design.

  • Type of pipe being used as per design drawings.

  • Are clearances to other services being maintained as per specification.

  • Does trench backfill material comply with standard drawings and specifications

  • Is the bedding material & thickness within tolerance and being compacted correctly

  • Is ground support suitable for the ground conditions and depth of excavation

  • Are end caps being used during construction where required.

  • Are boundary traps required on the project.

  • Have property branches been marked with PVC pipe to allow for asset recording purpose.

  • Has the concrete for manholes been placed and vibrated.

  • Is the surface finish of pit / manhole walls satisfactory.

  • Is compaction being done by contractor,and tested by registered contractor.

  • Are lids / covers as per design and correct rating.

  • Are pipes being stored on site as required.

1.4 Manhole-Inspection.

  • Have shields being used when manhole construction

  • Is form work adequate for the structure being constructed.

  • Does chase appear to be smooth and radial.

  • Do drop pipes and brackets appear to be in correct location.

  • Manhole hole / Inspection shaft located in the correct drawing design location.

  • Has construction of sewer main been within the correct easement area.

  • Step irons and Ladders spacing ok.

  • Have covers been greased at completion of works.

  • Connection to existing main been completed.

  • Have plugs been removed.

COMMENTS / PROGRESS / INSTRUCTIONS.

  • PHOTOS

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.