Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
WEATHER
- Hot
- Fine
- Showers
- Damp
- Wet
- Unsuitable for work
-
SITE CONDITIONS
- Hot
- Fine
- Showers
- Damp
- Wet
- Unsuitable for work
-
TRAFFIC MANAGEMENT
-
FENCING & O H &S SIGNAGE
1.0 ACTIVITY : Water.
-
Evidence of set out for works.
-
Water Sub Contractor Onsite
- Yes
- No
-
Copy of code standards available to workers on site.
1.2 Safety - Trenching, Pipelaying,Backfill
-
Have workers been provided with ladder were required in trench/sheild
-
Is lifting equipment suitable for the works being carried out.
-
Are hats and vests being worn by workers where required
-
Are trenches barricaded and made safe when left open.
1.3 Environmental - Earthworks, Excavation.
-
Does plant and equipment have suitable warning lights and reversing beepers
-
Is there provision to minimize dust / mud from leaving the site.
-
Are silt traps in place to prevent silt build up in previously installed drainage system.
-
Are environmental No Go areas fenced where required.
1.4 Works - Trenching, Pipe-laying,
-
Is there an accredited pipe layer on site where required.
-
Does the sub contractor have the current design.
-
Type of pipe being used as per design drawings.
-
Are pipes being installed as per design.
-
Are pipes being stored on site as required.
-
Are pipes being laid at correct depth.
-
Is ground support suitable for the ground conditions and depth of excavation.
-
Are trench widths adequate for pipe size/ type.
-
Does trench backfill material comply with standard drawings and specifications
-
Are clearances to other services being maintained as per specification.
-
Has the concrete for thrusts been placed as per design.
-
Property services being placed and marketed at completion of works section.
-
Are end caps being used during construction where required.
-
Has barrier/par webbing been placed around open holes waiting on further works.
-
Is compaction being done by contractor,and tested by registered contractor.
-
Has damaged road and footpaths been fixed after completion of works.
-
Has connection to water main completed
-
Has swabbing been under taken
- Yes
- No
1.4 Hydrant & Valve-Inspection
-
We're swabs marked with job number and numbers.
- Yes
- No
-
Fittings as per standard drawings
-
Hydrant covers as design drawings.
-
Depth of hydrant reflective of finished surface level.
-
Are valve covers and hydrant lids set up to finished levels.
-
Hydrant reflectors been placed on road surface.
-
Have hydrant marker's been placed at completion of works.
-
Are valve spindles on valves at acceptable height.
-
Have markings been placed on concrete kerb and channel to indicate service crossings.<br>
-
Top soiling been completed at end of works.
COMMENTS / PROGRESS / INSTRUCTIONS.
-
PHOTOS