Title Page
-
Report Date
-
Prepared by
Site 1
-
Site 1 - Location
-
Asphalt Operation - Estimated Duration to Complete
-
Existing overall road surface condition
- Excellent - No further treatment required
- Very good - Surface Intact, No potholing observed
- Good - Minor cracking.
- Adequate - Minor potholing
- Fair - Major potholing
- Expired - Advise immediate action
-
Existing Road Shape
-
Estimated Profiler Produced Material Overburden to Remove.
- + 100 Tonnes
- + 75 Tonnes
- + 50 Tonnes
- + 25 Tonnes
- + 10 Tonnes
- - 10 Tonnes
-
Existing kerb and Gutter Condition
-
Linemarking Replacement - Extent of Works
- THERMOPLASTIC - Extremely high
- WATER BOURN - Extremely high
- THERMOPLASTIC - Moderate
- WATER BOURN - Moderate
- THERMOPLASTIC - Average
- WATER BOURN - Average
- THERMOPLASTIC - Low
- WATER BOURN - Low
- THERMOPLASTIC - Slight
- WATER BOURN - Slight
- No linemarking reinstatement is required
-
Traffic Control (Asphalt Works) - Estimated Crew Numbers of Personal Required.
-
Traffic Control (Asphalt works) - Suggested Setup
- Stop / Go
- Contra - Flow
- Detour
- Road closure
- Chicane / Lane Switch
- Traffic Escort Vehicle
-
Traffic Control (Asphalt works) - Sign Sets Required
-
Existing Low Utility Services
-
Existing High Utility Services
Site 1 - Hazards
-
Overhanging Tree Branches
-
Low Powerlines
-
Unstable Pavement
-
Street Gradient
-
Street Lighting
-
Parked Cars
-
Site Access
-
Operations - Impact on Local Residents
Site 2
-
Site 1 - Location
-
Asphalt Operation - Estimated Duration to Complete
-
Existing overall road surface condition
- Excellent - No further treatment required
- Very good - Surface Intact, No potholing observed
- Good - Minor cracking.
- Adequate - Minor potholing
- Fair - Major potholing
- Expired - Advise immediate action
-
Existing Road Shape
-
Estimated Profiler Produced Material Overburden to Remove.
- + 100 Tonnes
- + 75 Tonnes
- + 50 Tonnes
- + 25 Tonnes
- + 10 Tonnes
- - 10 Tonnes
-
Existing kerb and Gutter Condition
-
Linemarking Replacement - Extent of Works
- THERMOPLASTIC - Extremely high
- WATER BOURN - Extremely high
- THERMOPLASTIC - Moderate
- WATER BOURN - Moderate
- THERMOPLASTIC - Average
- WATER BOURN - Average
- THERMOPLASTIC - Low
- WATER BOURN - Low
- THERMOPLASTIC - Slight
- WATER BOURN - Slight
- No linemarking reinstatement is required
-
Traffic Control (Asphalt Works) - Estimated Crew Numbers of Personal Required.
-
Traffic Control (Asphalt works) - Suggested Setup
- Stop / Go
- Contra - Flow
- Detour
- Road closure
- Chicane / Lane Switch
- Traffic Escort Vehicle
-
Traffic Control (Asphalt works) - Sign Sets Required
-
Existing Low Utility Services
-
Existing High Utility Services
Site 2 - Hazards
-
Overhanging Tree Branches
-
Low Powerlines
-
Unstable Pavement
-
Street Gradient
-
Street Lighting
-
Parked Cars
-
Site Access
-
Operations - Impact on Local Residents
Site 3
-
Site 1 - Location
-
Asphalt Operation - Estimated Duration to Complete
-
Existing overall road surface condition
- Excellent - No further treatment required
- Very good - Surface Intact, No potholing observed
- Good - Minor cracking.
- Adequate - Minor potholing
- Fair - Major potholing
- Expired - Advise immediate action
-
Existing Road Shape
-
Estimated Profiler Produced Material Overburden to Remove.
- + 100 Tonnes
- + 75 Tonnes
- + 50 Tonnes
- + 25 Tonnes
- + 10 Tonnes
- - 10 Tonnes
-
Existing kerb and Gutter Condition
-
Linemarking Replacement - Extent of Works
- THERMOPLASTIC - Extremely high
- WATER BOURN - Extremely high
- THERMOPLASTIC - Moderate
- WATER BOURN - Moderate
- THERMOPLASTIC - Average
- WATER BOURN - Average
- THERMOPLASTIC - Low
- WATER BOURN - Low
- THERMOPLASTIC - Slight
- WATER BOURN - Slight
- No linemarking reinstatement is required
-
Traffic Control (Asphalt Works) - Estimated Crew Numbers of Personal Required.
-
Traffic Control (Asphalt works) - Suggested Setup
- Stop / Go
- Contra - Flow
- Detour
- Road closure
- Chicane / Lane Switch
- Traffic Escort Vehicle
-
Traffic Control (Asphalt works) - Sign Sets Required
-
Existing Low Utility Services
-
Existing High Utility Services
Site 3 - Hazards
-
Overhanging Tree Branches
-
Low Powerlines
-
Unstable Pavement
-
Street Gradient
-
Street Lighting
-
Parked Cars
-
Site Access
-
Operations - Impact on Local Residents
Site 4
-
Site 1 - Location
-
Asphalt Operation - Estimated Duration to Complete
-
Existing overall road surface condition
- Excellent - No further treatment required
- Very good - Surface Intact, No potholing observed
- Good - Minor cracking.
- Adequate - Minor potholing
- Fair - Major potholing
- Expired - Advise immediate action
-
Existing Road Shape
-
Estimated Profiler Produced Material Overburden to Remove.
- + 100 Tonnes
- + 75 Tonnes
- + 50 Tonnes
- + 25 Tonnes
- + 10 Tonnes
- - 10 Tonnes
-
Existing kerb and Gutter Condition
-
Linemarking Replacement - Extent of Works
- THERMOPLASTIC - Extremely high
- WATER BOURN - Extremely high
- THERMOPLASTIC - Moderate
- WATER BOURN - Moderate
- THERMOPLASTIC - Average
- WATER BOURN - Average
- THERMOPLASTIC - Low
- WATER BOURN - Low
- THERMOPLASTIC - Slight
- WATER BOURN - Slight
- No linemarking reinstatement is required
-
Traffic Control (Asphalt Works) - Estimated Crew Numbers of Personal Required.
-
Traffic Control (Asphalt works) - Suggested Setup
- Stop / Go
- Contra - Flow
- Detour
- Road closure
- Chicane / Lane Switch
- Traffic Escort Vehicle
-
Traffic Control (Asphalt works) - Sign Sets Required
-
Existing Low Utility Services
-
Existing High Utility Services
Site 4 - Hazards
-
Overhanging Tree Branches
-
Low Powerlines
-
Unstable Pavement
-
Street Gradient
-
Street Lighting
-
Parked Cars
-
Site Access
-
Operations - Impact on Local Residents
Site 5
-
Site 1 - Location
-
Asphalt Operation - Estimated Duration to Complete
-
Existing overall road surface condition
- Excellent - No further treatment required
- Very good - Surface Intact, No potholing observed
- Good - Minor cracking.
- Adequate - Minor potholing
- Fair - Major potholing
- Expired - Advise immediate action
-
Existing Road Shape
-
Estimated Profiler Produced Material Overburden to Remove.
- + 100 Tonnes
- + 75 Tonnes
- + 50 Tonnes
- + 25 Tonnes
- + 10 Tonnes
- - 10 Tonnes
-
Existing kerb and Gutter Condition
-
Linemarking Replacement - Extent of Works
- THERMOPLASTIC - Extremely high
- WATER BOURN - Extremely high
- THERMOPLASTIC - Moderate
- WATER BOURN - Moderate
- THERMOPLASTIC - Average
- WATER BOURN - Average
- THERMOPLASTIC - Low
- WATER BOURN - Low
- THERMOPLASTIC - Slight
- WATER BOURN - Slight
- No linemarking reinstatement is required
-
Traffic Control (Asphalt Works) - Estimated Crew Numbers of Personal Required.
-
Traffic Control (Asphalt works) - Suggested Setup
- Stop / Go
- Contra - Flow
- Detour
- Road closure
- Chicane / Lane Switch
- Traffic Escort Vehicle
-
Traffic Control (Asphalt works) - Sign Sets Required
-
Existing Low Utility Services
-
Existing High Utility Services
Site 5 - Hazards
-
Overhanging Tree Branches
-
Low Powerlines
-
Unstable Pavement
-
Street Gradient
-
Street Lighting
-
Parked Cars
-
Site Access
-
Operations - Impact on Local Residents