Information
-
Audit Title. R44 - Earthworks - Topsoil strip. (Ed5 Rev 0) .
-
Document No.
-
Project Name:
-
Location:
-
Contractor
-
Prepared by
-
Conducted on
Work Activity Record
-
Cl 2.3 REMOVAL OF TOPSOIL.
-
Cl 2.3.1 Has clearing and grubbing been completed in the area.
-
Cl 2.3.1 Are erosion and sediment controls in place prior to commencing removal of topsoil?
-
Cl 1.7 Has the required action been taken to minimise the generation of excessive dust.
-
Cl 1.7 Have precautionary activities (such as sealing off) been implemented to minimise ingress of into the earthworks material.
-
Cl 2.3.1 Has the topsoil been left in place where bridging layers are to be used.?
-
Cl 2.3.2 Has a joint survey been carried out of the existing surface level at each stockpile site to latter determine the volume of topsoil placed.
-
Are the topsoil stockpiles <br>In a approved location.<br>. <br>. <br>
-
Are the topsoil stockpiles :<br>Free of subsoil and other excavated material.
-
Are the stockpiles :<br>Height not exceeding 2 metres
-
Are the stockpiles :<br>Batters been track rolled or stabilised
-
Are the stockpiles : <br>Been seeded within 7 days of completion of 500m2 of exposed batter face
-
Are the stockpiles :<br>Batter not exceeding 2H:1V
-
Ci 2.3.3
-
Has the Principal inspected the surface and released the hold point.
G22 Safety and G36 Environmental
-
G22 SAFETY
-
Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>
-
Has a SWMS been developed.
-
Is each and every item of plant being used for its designated and intended purposes.
-
Have the attachments for plant and processes been approved and used in accordance with their design and purposes.
-
Is the correct PPE being worn
-
Were any unsafe practices observed. <br>
-
Good safe practices observed.
-
G36 ENVIRONMENTAL
-
R44 Cl 1.7 Were erosion and sediment controls in place prior to the removal of any topsoil.
-
Are Erosion and Sediment controls measures being maintained.
-
Has mud been prevented from being deposited on roadways.
-
Have any environmental incidents or potential incidents been observed.
-
Good environmental procedures observed.
Compliance and Follow-up action.
-
Is the activity compliant.
-
Surveillance Officer
-
NCPN or memo number.
-
Follow up action
-
Product Non Conformance
-
System Non Conformance
-
Contractor generated NCR
-
Contractor generated a CAR
-
Matters arising
-
NCPN no
-
Contractors NCR no
-
CAR no
-
Closed out.
-
representative's name