Information

  • Audit Title. R44 - Earthworks - Topsoil strip. (Ed5 Rev 0) .

  • Document No.

  • Project Name:

  • Location:

  • Contractor

  • Prepared by

  • Conducted on

Work Activity Record

  • Cl 2.3 REMOVAL OF TOPSOIL.

  • Cl 2.3.1 Has clearing and grubbing been completed in the area.

  • Cl 2.3.1 Are erosion and sediment controls in place prior to commencing removal of topsoil?

  • Cl 1.7 Has the required action been taken to minimise the generation of excessive dust.

  • Cl 1.7 Have precautionary activities (such as sealing off) been implemented to minimise ingress of into the earthworks material.

  • Cl 2.3.1 Has the topsoil been left in place where bridging layers are to be used.?

  • Cl 2.3.2 Has a joint survey been carried out of the existing surface level at each stockpile site to latter determine the volume of topsoil placed.

  • Are the topsoil stockpiles <br>In a approved location.<br>. <br>. <br>

  • Are the topsoil stockpiles :<br>Free of subsoil and other excavated material.

  • Are the stockpiles :<br>Height not exceeding 2 metres

  • Are the stockpiles :<br>Batters been track rolled or stabilised

  • Are the stockpiles : <br>Been seeded within 7 days of completion of 500m2 of exposed batter face

  • Are the stockpiles :<br>Batter not exceeding 2H:1V

  • Ci 2.3.3

    no label
  • Has the Principal inspected the surface and released the hold point.

G22 Safety and G36 Environmental

  • G22 SAFETY

  • Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>

  • Has a SWMS been developed.

  • Is each and every item of plant being used for its designated and intended purposes.

  • Have the attachments for plant and processes been approved and used in accordance with their design and purposes.

  • Is the correct PPE being worn

  • Were any unsafe practices observed. <br>

  • Good safe practices observed.

  • G36 ENVIRONMENTAL

  • R44 Cl 1.7 Were erosion and sediment controls in place prior to the removal of any topsoil.

  • Are Erosion and Sediment controls measures being maintained.

  • Has mud been prevented from being deposited on roadways.

  • Have any environmental incidents or potential incidents been observed.

  • Good environmental procedures observed.

Compliance and Follow-up action.

  • Is the activity compliant.

  • Surveillance Officer

  • NCPN or memo number.

  • Follow up action

  • Product Non Conformance

  • System Non Conformance

  • Contractor generated NCR

  • Contractor generated a CAR

  • Matters arising

  • NCPN no

  • Contractors NCR no

  • CAR no

  • Closed out.

  • representative's name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.