Title Page

  • Project Name

  • Job Number

  • PFC ID

  • FED FROM - Switchboard ID and CB No.

  • Date

  • Prepared by

  • Position Title

  • Location

PFC Checklist

PFC Inspection - Pre-Energization

  • Confirm you have IFC/OEM drawings Onsite

  • Call your Supervisor to arrange for a set of drawings

  • Check & Perform proximity test at the switchboard

  • Check Isolation tags and locks installed at point of supply

  • Check All Circuit Breakers are in the Off position.

  • Check Labelling Against OEM Drawings

  • Check PFC is labelled with a "FED FROM" details

  • Check all covers/doors are available and fit correctly.

  • Check compartments no foreign objects, loose nuts, bolts, cut metal, tools.

  • Check compartments are free of metal fillings, cable ties etc– must be vacuumed & clean

  • Check compartments to ensure that all connections are tight

  • Check All Cable Entries are sealed and Glands are tight

  • Check that all contactors have free moveable contacts.

  • Check Visually the equipotential Earth Bond Connection (confirm all tight)

  • Check Visually all internal connections including Submains (confirm all tight)

  • PFC Submains are as per IFC/OEM Drawings (size & type)

  • PFC Main Switch is as per OEM Drawings (part number, rating & Assembly location)

PFC Controller

  • PFC Controller is as per OEM Drawings (part number & Assembly location)

  • Confirm and Check for Internal Fuses, Links and Control CBS - Isolate until energization

  • Check for loose Connections on the back of controller

  • Photo of the Controller Serial/Part Number

  • Is there a Control Neutral Installed for the PFC

  • Confirm size of Neutral

PFC CT

  • Confirm the CT has been install on A phase in the supply board

  • Confirm CT Ratio

  • Photo of the CT Ratio/Manufacture/Serial No.

  • Continuity Test (point to point) CT control cable from supply board to PFC Links

  • Remove CT jumper links in PFC - Test from controller to links to ensure connection.

  • PFC Capacitor
  • Capacitor is as per OEM Drawings (part number, rating & Assembly location)

  • Take Photos to capture Manufacturer, Serial Number, Ratings (A), (kVAR), System Voltage

Pre-Energization Tests

  • Test 1: Earthing System

  • The resistance of the main earthing conductor or any equipotential bonding conductor shall be not more than 0.5 Ohms.

  • EARTH TEST 1 - Supply Earth Bar to PFC Earth Bar

  • EARTH TEST 2 - PFC Earth Bar to PFC Equipotential Earth points

  • Test 2: Insulation Resistance

  • The Insulation Resistance between conductors should not be less than 1Mohm

  • Complete a battery test on IR tester before conducting any tests

  • Short IR tester leads to confirm working condition before conducting any tests

  • Select Testing Voltage

  • IR1 - A phase to B Phase =

  • IR2 - A Phase to C Phase

  • IR3 - B Phase to C Phase

  • IR5 - A Phase to Neutral

  • IR4 - B Phase to Neutral

  • IR6 - C Phase to Neutral

  • IR7 - A Phase to Earth

  • IR8 - B Phase to Earth

  • IR9 - C Phase to Earth

  • IR10 - Neutral to Earth

  • IR Test Results

  • Test 3: Polarity

  • The polarity testing shall show that all active, neutral and protective earthing conductors in the electrical installation are correctly connected to the corresponding terminals of electrical equipment.

  • Perform Polarity test by Shorting Phases to Earth

  • POL1 - A Phase to Earth

  • POL2 - B Phase to Earth

  • POL3 - C Phase to Earth

  • POL4 - Neutral to Earth

  • Note: Reconnect Neutral

  • Polarity Test Results

Final Pre-Energization Check List

  • SAFETY CHECK - This is HIGH RISK WORKS, ALL WORKS TO BE DONE CAREFULLY and WITH CAUTION. Follow the SWMS and safe work procedures. REMEMBER to treat All equipment as energized until proven "DEAD".

  • 5.1 Do you have a copy of the Permit to energize.

  • 5.2 Has a Site Toolbox been completed with ALL staff including other trades notified of the energization.

  • 5.3 Has the work areas been made safe with the correct exclusion zones put in place

  • 5.4 Has the correct notice of energization signage be install on the boards

  • 5.5 Confirm the ALL JLE staff have signed onto and are aware of the steps in SWMS (TBC)

  • 5.6 Confirm Switching Procedure and All other Isolations points have been locked out and tagged.

  • 5.7 Confirm All Internal Fuses, Voltage link and Control CBS are turned "On"/ Installed

  • 5.8 Confirm Both ends are made safe and ready to energise

  • 5.9 All covers and escutcheons have been install

  • I have completed all the Final Checks and happy to procedure with Energization

  • Date and Time

PFC Post Energization Tests

  • Switching has been completed and equipment ready for testing

  • Test 1: 6 Point Voltage Test

  • Phase to Phase Voltage 415v = Phase to Earth Voltage = 240v. Read the results out loud

  • VT1 - A phase to Earth

  • VT2 - B phase to Earth

  • VT3 - C phase to Earth

  • VT4 - A phase to B Phase

  • VT5 - A phase to C phase

  • VT6 - B phase to C phase

  • 6 point voltage test Results

  • Witness Photo of Results

  • Test 2: Phase Rotation

  • Test Location: Energized Equipment Line side of Main Switch

  • Connection Method: Red, White, Blue leads on meter to match the Circuit Left to right (Not the cable colours)

  • Rotation test

  • Mark Rotation on the PFC

  • Photo of the results

  • Isolate and roll A and B phase at the source

  • Rotation test 2

  • Mark Rotation on Switchboard

  • Photo of results

  • Contact your supervisor stop tests

  • Rotation MUST be clockwise - Stop and call your supervisor.

  • Turn On PFC Main Switch

  • Follow OEM Procedure for Programming controller.

  • Quick set up will involve confirming Supply Voltage, CT ratio, Auto/Man, Switching timing etc

  • Fill out the Customer Setting page in OEM Manual. (Tick if as per default, Add New setting if changed from default). Take a Photo of the settings

  • Test voltage at CT links in PFC (Volatge to be < 1v AC.)

  • IF Voltage is greater than 1v then re check connections

  • Check the Display Current Matches the Current at the supply CT

  • IF No load use a 10A load box on A phase to simulate a load

  • Check the Display Voltage Matches the Supply Voltage

  • Perform a functional check of Cooling Fans.

  • If thermostat controlled reduce the cut in temp. If no thermostat then bridge the controller terminals.

  • Test PFC Capacitor Step
  • Capacitor size

  • Manually switch the Step "On"

  • Tong A phase

  • Tong B phase

  • Tong C phase

  • Confirm Phase Voltage at Capacitor

Test Equipment Details

  • Insulation Tester

  • Make/Model:

  • Serial Number:

  • Calibration Due Date:

  • Mutli-Meter

  • Make/Model:

  • Serial Number:

  • Calibration Due Date:

  • Clamp Meter

  • Make/Model:

  • Serial Number:

  • Calibration Due Date:

  • 10A Load Bank

  • Photo of Remote Earth

Report Sign Off

  • Mark Up/Highlight Projection Study As Builds and Take a Photo

  • Onsite Sign Off: I am Satisfied that the PFC within this report meets the design Specifications provided

  • Engineer Review: I have reviewed the PFC results Inspected in this report and confirm that they meet the design specifications.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.