Title Page
-
Project Name
-
Job Number
-
Switchboard Number
-
Date
-
Prepared by
-
Position Title
-
Location
Bus Bar Inspection
Visual Inspection
-
Remove all Bus/Cable Zone Covers
-
Bus/Cable Zone should be checked and must be confirmed it is clean & free of any loose items
-
Check Bus Bar Joints for loose connections (confirm witness marks)
-
Select a random portion of joints and complete a torque cross check
-
Witness Photos of Bus Bar Zone and Joints
Insulation Resistance Test
-
Disconnect/Remove M.E.N Link
-
Disconnect/Remove Electronic devices
-
Disconnect/Remove Surge Devices
-
Disconnect/Remove Fuses
-
Open All Circuit Breakers
-
Results to be Achieved: The Insulation Resistance between conductors should not be less than 1M ohm
-
A Phase to Earth
-
B Phase to Earth
-
C Phase to Earth
-
A Phase to Neutral
-
B Phase to Neutral
-
C Phase to Neutral
-
A Phase to B Phase
-
A Phase to C phase
-
B Phase to C Phase
Report Sign Off
-
Onsite Sign Off: I am Satisfied that the Bus Bar inspected in this report meets the design specifications provided.