Title Page
-
Bus number
-
Site conducted
-
Conducted on
-
Prepared by
VF463 - SMC Door Installation Checklist
Chassis Section Checklist
-
Check that the door aperture size is correct as per reference drawing. <br>Front Door: Height& Width<br>Centre Door: Height & Width
-
Front Door: Height & Width
-
Centre Door: Height & Width
-
Check that the door aperture is square.
-
Front Door:
-
Rear Door:
-
Check correct fasteners have been fitted. As per engineering drawing
-
Front Door
-
Rear Door
-
Check that the door mechanism plates are installed in correct position and are fastened securely. ( Centre of door aperture ) Reference to general arrangement drawing if required.
-
Front Door
-
Centre Door
-
Check door mechanism plates are mounted level.
-
Front Door
-
Rear Door
Construction Section checklist for Inward Gliding Doors & Rapid sliding Door
-
Check both door shafts are installed correctly.
-
Front Doors
-
Check that the both door shafts are parallel with the body and aperture.
-
Front Doors
-
Check both door leafs are installed correctly.
-
Front Doors
-
Are both door leafs parallel and does the lip on the nosing rubber on the front leaf lie on the outside of the rear leaf. Check the clearance between the aperture side and the door leafs. Check that the door leafs are square in the aperture. If not adjust the doors. See VENTURA door installation guide.
-
Front Doors
-
Check that the door leafs are installed correctly. Is the outside of door leafs up against the aperture seal when doors are closed.
-
Front Doors
-
Check that the top of the door leafs on outside of bus are in line with the profile of the bus. If not adjusted. See VENTURA door installation guide.
-
Front Doors
-
Check aperture seal if fitted correctly.
-
Front Doors
-
Are the sensitive edge wires in a non-strained and free of pinching when the doors are opened & closed.
-
Front Doors
-
Check power supply. Check door leafs are moving smoothly open / closed. Check for any obstructions (loose parts, wiring or tubes) Check guiding brackets run smoothly through the guiding rail. Check door leafs are perpendicular with step edge. Check the pneumatic system (if applicable) for leakage during opening & closing.
-
Front Doors
-
Check all torque settings have been completed. See VENTURA door installation guide.
-
Front Doors
-
Check the door shaft is mounted correctly. See VENTURA door installation guide.
-
Centre Door
-
Check the upper door arm is mounted correctly. See VENTURA door installation guide.
-
Centre Door
-
Check door leaf is mounted correctly. See VENTURA door installation guide.
-
Centre Door
-
Check door leaf is parallel with step edge. See VENTURA door installation guide.
-
Centre Door
-
Check door leaf is level and height is set correctly in aperture. See VENTURA door installation guide.
-
Centre Door
-
Check door leaf in closed position is flush with outside surface of aperture. See VENTURA door installation guide.
-
Centre Door
-
Check door leaf aperture seal in fully closed position is flush with outside surface of the aperture. See VENTURA door installation guide.
-
Centre Door
-
Check door leaf is moving smoothly through open & closed position.
-
Centre Door
-
Check there are no obstructions ( ex: loose parts, wires or tubes )
-
Centre Door
-
Check the seal between door leaf, the aperture and the floor is sufficient.
-
Centre Door
-
Check the pneumatic system (if applicable) for leakage during opening & closing.
-
Rear Door
-
Check the emergency buttons operate.
-
Rear Door
-
Check all torque settings have been completed. See VENTURA door installation guide.
-
Rear Door