  • Audit Title

  • Document No.

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Pre Work Inspection ( to be completed prior to beginning work)

  • Plans have been picked up and signed for.

  • Purchase order has been received. <br>

  • Permits have been received.

  • Necessary framing ( chases, etc.) are complete.

  • Temporary stairs are in place.

  • Temporary handrails are in place.

  • Safety bracing is in place.

  • Plumber has completed work, pipes are in place etc.

  • Interior work area is clean and free of debris.

  • Site is clean and free of debris.

  • Electricity is available.

  • If units are to be set in attic, the scuttle hole for the attic HVAC equipment access is framed, the HVAC unit area is floored, and adequate working area is available.

  • House is roofed and shingles are installed.

  • HVAC units have been verified for correct type and tonnage.

  • Site Superintendent:

  • Trade Contractor: Company Name (printed)

Final Inspection: (to be completed before Trade Contractor leaves job site)

  • Heating unit(s) has been set with necessary clearances on all sides.

  • No ductwork is crimped, bent, or damaged so as to restrict airflow.

  • Adequate space in heating unit area has been verified so that ductwork will not obstruct necessary maintenance, changing of filters, etc.

  • Attic unit is properly set, and ducts are not crimped, bent, or otherwise damaged if unit are to be placed in attic.

  • All piping to the exterior of the house is complete and sealed properly.

  • All ducts are properly sealed to boots.

  • All ducts are properly sealed to the heat exchanger.

  • All ductwork is properly secured.

  • All air returns and vents are properly sealed to floor and placed per plan.

  • All flor ducts are securely covered.

  • All gas cutoffs are installed properly and are accessible. (fireplace, clothes dryer, furnace, etc.)

  • Locations of thermostats are correct per plan.

  • Gas pressure is adequate.

  • System has passed rough HVAC inspection. Attach picture of report.

  • House is broom swept and clear of debris.

  • No debris is left on lot.

Summary

  • Date: Project superintendent:

  • Trade Contractor: Company Name:

  • Project manager

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.