Information

  • H9 BLASTING USING EXPLOSIVES .

  • Project Name: Tabulam New Bridge.

  • Location: BRUXNER HIGHWAY TABULAM

  • Contractor

  • Prepared by

  • Conducted on

Work Activity Record

  • N.A Not Applicable. N.C Not Checked

  • 1 Has blasting been approved under the project environmental conditions of approval?

  • 2 Has a blast management plan been prepared, approved and available on site?

  • 3 Does the plan include a procedure to address misfires?

  • 4 Is there a procedure to manage traffic and minimise delays associated with blasting (e.g.<br>TMP/TCPs)?<br>

  • 5<br>Is there a requirement for the assessment of the weather prior to blasting and during loading?

  • 6<br>Is there a requirement to assess risk of fall adjacent to cut batter slopes pre/post blasting?

  • 7<br>Does the shotfirer have a current WorkCover blasting explosive user licence?<br>

  • 8<br>Do all personnel handling explosives have a licence?

  • 9<br>Do the quantities of explosive/s being transported require a licence? Is a copy of the licence/s available on site?

  • 10<br>Has approval by WorkCover been granted for storage of explosives on site?

  • 11<br>Is a copy of the site security plan available?<br>

  • 12<br>Has the contractor developed a loading sequence plan to address the safety of personnel and general public?

  • 13<br>Are all blasting consumables stored securely and are site plans in place to manage the security of boosters and detonators?

  • 14<br>Does the plan address the timing of priming holes?<br>

  • 15<br>Has the Contractor provided a method to isolate the blast area during loading/charging of holes?

  • 16<br>Has the Contractor provided a method to prevent contamination of holes post drilling?

  • 17<br>Are precautions taken to ensure that the safety fuses, lead wires, detonating cord or signal tube connected to the primer are not damaged during the placing of stemming material and subsequent tamping?

Compliance and Follow-up action.

  • Is the activity compliant.

  • Surveillance Officer

  • NCPN or memo number.

  • Follow up action

  • Product Non Conformance

  • System Non Conformance

  • Contractor generated NCR

  • Contractor generated a CAR

Matters arising

  • NCPN no

  • Contractors NCR no

  • CAR no

  • Closed out.

  • RMS representative's name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.