H11 WORK NEAR OVERHEAD UTILITIES .
-
Project Name: Tabulam New Bridge.
-
Location: BRUXNER HIGHWAY TABULAM
-
Contractor
-
Prepared by
-
Conducted on
Work Activity Record
-
N.A Not Applicable. N.C Not Checked
-
1<br>Is there another way of undertaking the work that would eliminate the need to work within the “no go” zones?
-
2<br>Has the network operator been consulted regarding the proposed work?
-
3 Does the plan include a procedure to address misfires?
-
4 <br>Have staff involved in the work been trained in controlling risks from overhead utilities in the vicinity of work sites?<br>
-
5<br>Have safe work method statements been developed for working near overhead utilities and are staff trained in following these work methods?
-
6<br>Have plans and other relevant information about the overhead utilities been obtained?
-
Has the location of overhead utilities been plotted on the work area plan?<br>
-
8<br>Has all information concerning the location of utilities been given to the responsible supervisor or contractor at the work site?
-
9<br>Has allowance been given to variations in the sag of the line at different times of the day?
-
10<br>Has allowance been given to the sway of the lines, particularly if wind conditions change during the work period?
-
11<br>Are relevant authorities notified of any inconsistencies between the information they provided and the actual locations of the utilities?<br>
-
12<br>Are the minimum working distances specified in the Code of Practice been complied with:<br>8 m, for > 330kV<br>6 m, for > 132kV but < 330kV<br>3 m, for <132kV
13 If working within the approach distances, has:
-
a spotter been designated to observe the operation of the plant,<br>
-
the plant operator and the spotter completed “Crane and plant Electrical Safety” course?
-
14<br>Is the supply authority told when work in the vicinity of overhead utilities has been completed and is a record kept of notification?
Compliance and Follow-up action.
-
Is the activity compliant.
-
Surveillance Officer
-
NCPN or memo number.
-
Follow up action
-
Product Non Conformance
-
System Non Conformance
-
Contractor generated NCR
-
Contractor generated a CAR
Matters arising
-
NCPN no
-
Contractors NCR no
-
CAR no
-
Closed out.
-
RMS representative's name