  • H11 WORK NEAR OVERHEAD UTILITIES .

  • Project Name: Tabulam New Bridge.

  • Location: BRUXNER HIGHWAY TABULAM

  • Contractor

  • Prepared by

  • Conducted on

Work Activity Record

  • N.A Not Applicable. N.C Not Checked

  • 1<br>Is there another way of undertaking the work that would eliminate the need to work within the “no go” zones?

  • 2<br>Has the network operator been consulted regarding the proposed work?

  • 3 Does the plan include a procedure to address misfires?

  • 4 <br>Have staff involved in the work been trained in controlling risks from overhead utilities in the vicinity of work sites?<br>

  • 5<br>Have safe work method statements been developed for working near overhead utilities and are staff trained in following these work methods?

  • 6<br>Have plans and other relevant information about the overhead utilities been obtained?

  • Has the location of overhead utilities been plotted on the work area plan?<br>

  • 8<br>Has all information concerning the location of utilities been given to the responsible supervisor or contractor at the work site?

  • 9<br>Has allowance been given to variations in the sag of the line at different times of the day?

  • 10<br>Has allowance been given to the sway of the lines, particularly if wind conditions change during the work period?

  • 11<br>Are relevant authorities notified of any inconsistencies between the information they provided and the actual locations of the utilities?<br>

  • 12<br>Are the minimum working distances specified in the Code of Practice been complied with:<br>8 m, for > 330kV<br>6 m, for > 132kV but < 330kV<br>3 m, for <132kV

13 If working within the approach distances, has:

  •  a spotter been designated to observe the operation of the plant,<br>

  •  the plant operator and the spotter completed “Crane and plant Electrical Safety” course?

  • 14<br>Is the supply authority told when work in the vicinity of overhead utilities has been completed and is a record kept of notification?

Compliance and Follow-up action.

  • Is the activity compliant.

  • Surveillance Officer

  • NCPN or memo number.

  • Follow up action

  • Product Non Conformance

  • System Non Conformance

  • Contractor generated NCR

  • Contractor generated a CAR

Matters arising

  • NCPN no

  • Contractors NCR no

  • CAR no

  • Closed out.

  • RMS representative's name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.