Title Page

  • Site conducted

  • Audit Title

  • Project Name

  • Conducted on

  • Prepared by

  • Location
  • Instructions
    -------------------
    1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
    2. Add photos and notes by clicking on the paperclip icon.
    3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
    4. Complete audit by providing digital signature.
    5. Share your report by exporting as PDF, Word, Excel or Web Link

Composite roof

  • Main Contractor:

  • Project Number:

  • Issued to:

  • QA Sheet No:

  • Elevation:

  • Level:

  • Comments:

STRUCTURE

  • Primary structure handover complete.

  • Personnel

Storage

  • Store the material in dry protected conditions, never stacked more than two pallets high.

  • Personnel

Installation Checks

  • 8mm diameter bead mastic installed on eaves purlin.

  • Personnel

  • 8mm bead mastic installed onto ridge line or hip cleader.

  • Personnel

  • Panel end laps - bottom panel to have minimum 10mm bearing onto purlin.

  • Personnel

  • 6mm x 5mm strip mastic installed at panel end laps - rows above and below fixing point, 1 row 5mm back from end of panel

  • Personnel

  • Check end laps for ineffective seals and seal as necessary.

  • Personnel

  • 3nr primary fixings per panel per purlin - fastener positioned in centre of each corrugation.

  • Personnel

  • 6mm x 5mm strip mastic installed to panel side laps.

  • Personnel

  • Panel side laps stitched as per manufacturers recommendations.

  • Personnel

  • Ridge flashing with 150mm end laps sealed with 2nr runs of butyl mastic and stitched onto each roof corrugation. 6 fixings across ridge at end laps.

  • Personnel

  • Ridge fillers to be sealed top and bottom and set back 80mm from edge of ridge flashing.

  • Personnel

Completion

  • Installer Signature:

  • A2O Signature:

  • Client Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.