1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
Neaco Decking
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Building:
-
Elevation:
-
Level
-
Comments:
STRUCTURE
-
Is the existing structure free from structural damage
-
Is the existing EPDM to the balcony free from damage
-
Hold Point
Remedial Works
-
Are all voids closed off as per details with either Fire Pro 700 sealant or RWA 45 and Galvanised closers
-
Hold Point
Fixings and Clips
-
Have the correct fixings been used with correct centres
-
Personnel
- Installer
- A2O
-
Have the clips been used with the fixings and engaged properly
-
Personnel
- Installer
- A2O
-
Hold Point
Decking Planks and Trims
-
Have the decking planks been cut to allow movement around to the perimeter of the steel balcony
-
Personnel
- Installer
- A2O
-
Has the cover trim been installed as per the drawings with correct fixings and centres
-
Personnel
- Installer
- A2O
-
Hold Point
Final Checks
-
Has all the waste material been removed from the balcony
-
Personnel
- Installer
- A2O
-
have all sharp edges been removed
-
Personnel
- Installer
- A2O
-
Is the new decking free from damage and clean
-
Personnel
-
Hold Point
Completion
-
Installer Signature:
-
Supervisor Signature:
-
Management Signature: