  • Document No.

  • Site / Company

  • Conducted on

  • Prepared by

  • Personnel interviewed and accompanying auditor

Procedure

  • Is there a written and approved site procedure for Hot Work?

  • Has it been communicated to the employees ?

  • Has it been communicated to the contractors?

  • Are supervisors in charge of work groups that are required to undertake Hot work operations trained in the SLAM and or JHA methods and received training in the specific hazards, risks and controls that apply to hot work and given the responsibility by the Engineering manager of Authorized Hot Work permit issuer ?

  • As a minimum SLAM is completed for all Hot work tasks?

  • Is the HWA complete the Hot work permit form and address the questions presented on that form and identify the necessary steps to eliminate or control the hazards identified and documenting on the hot work permit form

  • Is the Hit work permit form presented to WPI in charge for review and approval?

  • Where the risk assessment is high with controls in place then a full JHA is undertaken?

  • Is the HWA implement the risk control measures listed on the Hot work permit before commencing the Hot work?

  • Is any person acting as Fire watch trained in the use of fire extinguisher and fire hoses and any other fire fighting equipment?

  • Is the HWA aware if any of the hazards or risks change during the course of the hot work them the hot work stopped until such time as the hazard ps and risks presented by the change have been reassessed by the HWA and reported to WPI?

  • On completion of the Hot work, is the HWA satisfies himself that the conditions on the hot work permit have been satisfied including necessary fire watch and clean up and making safe of the job site after which he can sign off the hot work as complete on the hot work permit and take the permit to WPI for sign off

  • Is the WPI satisfied himself or herself that the work location and vicinity are left safe and no further residual risk of fire or ignition exists before signing off closure of the hot work permit

Record management

  • Are the closed hot work permit returned to the engineering secretary for filing ?

  • All closed hot work permits filed by the engineering secretary and kept for 12 months in an active file?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.