Project Information

  • Document No.

  • Part No.

  • Revision No.

  • Client Name

  • Project Name

  • Inspection Started

  • Prepared by

  • Location

Test Details

  • Drawings Supplied

  • Drawing Number

  • Drawing Revision

  • Drawing Date

  • Drawing Approval RPEQ

  • Specifications Required

  • Structures to be Tested

  • Structure
  • Structure Identification Details

  • Structure Depth (mm)

  • Actual Depth?

  • Structure Diameter

  • Actual Dimentions?

  • Is the Structure Covered?

  • Start Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Weather

  • Day 1

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Day 2

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Day 3

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Day 4

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Day 5

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Day 6

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Day 7

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Start Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Day 1

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Day 2

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Day 3

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Day 4

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Day 5

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Day 6

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Day 7

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Structures to be Tested

  • Structure
  • Structure Identification Details

  • Structure Depth (mm)

  • Actual Depth?

  • Is the Structure Covered?

  • Start Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Weather

  • Complete Test

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Evaporation Pan Temperature

  • Evaporation Pan Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Weather

  • Start Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Complete Test

  • Completion Time

  • Structure Water Temperature

  • Ambient Temperature

  • Structure Water Level Outside Ruler

  • Water Level Drop from Previous Day

  • Structure Diameter

  • Actual Dimentions?

Test Procedure

Confirm Project Information

  • Structures to be inspected and their details

  • Testing specification requirements

Initial Work Area Inspection

  • Is test area barricaded off or sufficiently delineated?

  • Is traffic control established?

  • Has a Confined Space Risk Assessment & Entry Permit been completed?

  • Has a Safe Work Method Statement been completed and all control measures followed?

  • Is the confined space equipment and procedures set up as per the Risk Assessment & Entry Permit conditions followed?

  • Structure lid removed and placed at a safe distance from the entry point

Inspection Steps

  • Equipment checked and in good working order

  • Insert plugs into structure inlets with extendable pole if possible

  • Inflate plugs and add support as per manufacturer's specifications

  • Place level across structure access hole and measure from the middle of the underside of level to top of water level using a hard ruler

  • If applicable, set up and record evaporation pan and complete test as per the same procedure

  • Observe water level for time specified in specifications and record result

Disassemble Steps

  • Pump or release water from structure, release pressure from plugs and carefully retrieve plugs out of structure

  • Replace structure lid, remove barricading and return all items to test unit

Final Demobilisation

  • Notify client of result and to contact TestX office to arrange further testing or reports

  • Inspector's remarks

  • Photo of work area and inspected structures

  • I declare that the inspection procedure was followed in accordance with the nominated specifications

  • Inspection Completed

  • Report Issue Date

Report Approval - Cam Reid

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.