Project Information

  • Document No.

  • Part No.

  • Revision No.

  • Client Name

  • Project Name

  • Inspection Started

  • Prepared by

  • Location

Test Details

  • Drawings Supplied

  • Drawing Number

  • Drawing Revision

  • Drawing Date

  • Drawing Approval RPEQ

  • Specifications Required

  • Pipeline Construction Type

  • Test Method WSA06-2008-1.2, Clause 41.4.4

    Initial Vacuum Pressure = -80kPa
    Settle Time = 3 minutes
    Test Hold Pressure = -80kPa
    Hold Time = 3 Hours
    Allowable Loss in Nominated Timeframe = 3kPa

  • Pipelines to be Tested

  • Pipeline
  • Pipeline Identification Details

  • Pipeline Diameter

  • Actual Diameter (mm)

  • Pipeline Length (m)

  • RESULT

  • Pipeline Construction Type

  • Enter details of Project Specifications Must include initial vacuum pressure, settle time, allowable time and final drop vacuum pressure

  • Pipelines to be Tested

  • Pipeline
  • Pipeline Identification Details

  • Pipeline Diameter

  • Actual Pipeline Diameter

  • Pipeline Length (m)

  • RESULT

Test Procedure

Confirm Project Information

  • Pipelines to be inspected and their details

  • Testing specification requirements

Initial Work Area Inspection

  • Is test area barricaded off or sufficiently delineated?

  • Is traffic control established?

  • Has a Safe Work Method Statement been completed and all control measures followed?

  • Has a Confined Space Risk Assessment & Entry Permit been completed?

  • Is the confined space equipment and procedures set up as per the Risk Assessment & Entry Permit conditions followed?

  • Structure lids removed and placed at a safe distance from the entry point

  • Environmental controls installed as and if required

Inspection Steps

  • Equipment checked and in good working order

  • Attach pipeline via threaded fitting to vacuum pump and vacuum down line as per specifications

  • Allow for vacuum to stabilise for an amount of time as per specifications

  • Hold vacuum for time specified in specifications and record result

Disassemble Steps

  • Disconnect hose from vacuum pump and release pressure from pipeline

  • Replace structure lids, remove barricading and return all items to test unit

Final Demobilisation

  • Notify client of results and to contact TestX office to arrange further testing or reports

  • Calibrated gauge numbers used

  • Inspector's remarks

  • Photo of work area and inspected pipeline

  • I declare that the inspection procedure was followed in accordance with the nominated specifications

  • Inspection Completed

  • Report Issue Date

Report Approval - Cam Reid

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.