Title Page
-
Audit Title
-
Job Description
-
Service Provider
-
Subcontractor
-
Crew Leader
-
Location
-
Conducted on
-
Prepared by
Audit Protocol for MG SWP CP5.002
6.1 – Start Chart
-
Has the most favourable site been chosen for the installation of the ICCP?
6.2 – Prepare Pipeline for Cathodic Protection
-
Have the requirements been met to provide effective cathodic protection?
6.3 – Determine Current Requirements
-
Were current density requirements determined through testing and investigation?
6.4 – Determine Location of Underground Assets
-
Have Dial Before You Dig (DBYD) plans been obtained?
6.5 – Measure Soil Resistivity at Selected Sites
-
Has a field survey been completed for the location?
-
Has the soil resistivity been tested correctly following the procedure MG SWP CP3.007 Soil Resistivity Measurement?
6.6 – Determine Anode Ground Bed Configuration
-
Was the Design Calculation spreadsheet used correctly to determine the anode bed design?
-
Is the DC voltage suitable?
6.7 – Determine Output Capacity of CPU
-
Has MG PR WP-CP5.001 been used to design the transformer/rectifier?
-
Has the output capacity of the CPU been calculated correctly?
6.8 – Submit Conceptual Design for Review by Supervisor
-
Were the conceptual design drawings submitted to the Supervisor?
6.9 – Is conceptual design acceptable?
-
Did the Supervisor sign off on the design drawings?
6.10 – Revise and Resubmit Conceptual Design
-
If required, have the drawings been revised and resubmitted?
6.11 – Complete Detailed Design
-
Has the detailed design been completed in line with MG PR WP-CP6.004?
6.12 - Finish
Comment & Sign Off
-
Comment & Audit Finding Summary
-
Auditor(s) Sign Off
-
Auditee (Crew Leader) Sign Off