Title Page
-
Audit Title
-
Job Description
-
Service Provider
-
Subcontractor
-
Crew Leader
-
Location
-
Conducted on
-
Prepared by
Audit Protocol for MG SWP CP6.005
6.1 – Work Area Safety
-
Work site has been prepared for Thermit Welding and permits obtained?
6.2 – Distance from Other Welds
-
6.2 – Distance from Other Welds
6.3 – Surface Preparation
-
Have surfaces been prepared for Thermit weld?
6.4 – Wall Thickness Check
-
Has the thickness of the material to be welded been measured and recorded?
6.5 – Cable Preparation
-
Have the cable strands been prepared for the weld?
6.6 – Mould and Cable Positioning
-
Has the mould been secured and cables positioned correctly?
6.7 – Mould Load and Firing
-
Has the charge been loaded correctly in the mould?
-
All required safety PPE is worn during firing of charge?
6.8 – Weld Inspection
-
Is the weld successful?
-
If the weld fails, was the new weld performed correctly?
6.9 – Clean Up
-
Have all finished welds and work area been cleaned and made safe?
6.10 – Coating Repair
-
Has the pipeline coating been repaired according to MGN standards?
6.11 – Finish
-
Have the location details for this cable connection been recorded as per the relevant work procedure?
Comments and Sign Off
-
Comments and Audit Findings Summary
-
Auditor(s) Sign Off
-
Auditee (Crew Leader) Sign Off