Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site Office
SITE OFFICE
-
Site Establishment Plan - On display?
-
Emergency Contact Details - On display?
-
Emergency Evacuation Instructions - On display?
-
Evacuation Siren - available and tested?
-
Visitor Register - Available and in use?
-
Is the First Aid cabinet suitably stocked with contents date current?
-
Fire Extinguisher tags up-to-date? (6 months)
Lunchrooms
-
Clean and tidy?
-
Emergency Evacuation Instructions - On display?
Safety Noticeboard
-
OHS Policy - On display?
-
Environmental Policy - On display?
-
OHS Representative - Name on display?
-
Site Establishment Plan - On display?
-
Emergency Evacuation Instructions - On display?
-
Toolbox meeting minutes - On display?
Toilets
-
Toilets in functioning order?
-
Toilet paper, Soap & Hand towel stocked?
-
Are any taps or fixtures leaking water?
-
Toilets cleaned weekly?
Signage
-
Entry Signage displayed at front gate and in good condition?
-
Safety signage is appropriate for the site?
-
Cooper & Oxley identification and registration number displayed?
-
Emergency Muster Point - sign located at Muster Point?
-
Site Office & First Aid locations easily identifiable?
Safe Work Method Statement Complaince
- Subcontractor SWMS
-
Subcontractor Name:
-
SWMS Title:
-
Observed work is in compliance with SWMS?
-
SWMS reviewed and resigned monthly?
-
Is a review of the SWMS required?
Electrical
-
Site shed RCD's test/tagged (6 monthly)
-
Electrical tools test/tag - random inspection (subcontractor, tool, tag number, name of tester)
-
Power Boxes - Numbered and test/tagged?
-
Power Boxes - Leads entering through correct entry holes?
-
Power Boxes - RCD push button tested?
-
Power Boxes labelled appropriately? (I.e electrical hazard warning sign, board ID, supply location)
-
Any leads on the ground or hanging from steel structures?
-
Lead stands/hangers in use and insulated?
-
Leads no longer than 30m in use?
Excavations
-
Excavation Permit has been completed, including details of the defined SWMS?
-
Barricading erected around excavation areas?
-
Excavations with a potential to collapse inward, benched, battered or shored?
-
Plant and spoil kept or placed at least 1m from edge of excavation?
-
Spoil or stock piles kept away from drains, buildings, fences, trees?
-
Excavations have safe means of access/egress?
-
Daily excavation checklists completed as required?
Working at Height
- Powered Plant/Equipment
-
Subcontractor:
-
Plant ID:
-
Plant risk assessment submitted to site?
-
Plant maintenance records submitted to site?
-
Plant logged into plant/equipment register?
-
Plant specific SWMS signed?
-
Daily pre-start checks completed?
-
Plant free from obvious leaks?
-
Maintenance identified in pre-start has been communicated to those responsible?
-
Plant operators hold current licence or competency?
-
Lifting slings, chains, harnesses, fire extinguishers etc. certified/tagged?
-
Are appropriate machine guards in place?
-
Plant is being operated clear of overhead power lines?
-
Plant being operated at a site specific speed limit?
-
Seat restraints being used correctly?
Powered Plant & Equipment
SCAFFOLD
-
Last scaffold inspection within 30 days?
-
Scaf tags updated and legible with inspector name?
-
Scaf tags at all scaffold entry points?
-
Are feet centrally located on sole boards?
-
Edge protection complaint with:<br>Guard rail, mid rail, toe boards, or;<br>Guard rail and mesh panel
-
Work platform clean and free from obstructions?
-
Scaffold 4m and above, erected by licensed scaffolder?
LADDERS
-
Ladders extend a minimum of 1m above connection point and are secured (I.e tie down)
-
Ladders are maintained in good condition?
-
Step ladders have legs correctly spaced and locked/tied off?
-
Top step of step ladder being used as a working platform?
-
Defective ladders tagged out of service and placed in quarantine area?
OPEN FLOOR PENETRATIONS
-
Holes or openings in floors are barricaded or boarded with danger signs
GUARD RAILS
-
Guard rails in place where a person can fall 2m or more from a stair, landing or fixed platform?
FALL ARREST/RESTRAINT
-
Harness tagged? (6 monthly)
-
Harness in use and attached or anchor point?
-
Working at Height Permit has been completed, including details of the defined SWMS?
Hazardous Substances and Dangerous Goods
-
Hazardous substances register is up to date?
-
Hazardous substances assessed as High risk or above, have been approved by Site Manager?
-
MSDS register and file up to date?
-
Storage facility is labelled HAZCHEM?
-
Storage facility is well ventilated and away from potential ignition sources?
-
All Hazardous substances appropriately labelled?
-
Gas cylinders secured?
-
Gas cylinders have flashback arresters in use?
-
Incompatible chemicals segregated?
-
Spill kit proportionate to size of project available?
-
Subcontractor hazardous substances stored correctly?
Personal Protective Equipment
-
Mandatory PPE is being worn by subcontractors?
-
PPE is in good condition?
-
Task specific PPE is being used?
Other
-
Subcontractor sheds/sea containers tidy with correct storage requirements
-
Quarantine area established and orderly to house out of service items?
-
Star pickets/reinforcing rods protected by caps?
-
All other work permits have been completed, including details of the defined SWMS?
-
Site safety documentation properly completed and filed away?
-
Public safety controls remain effective (fencing, locks, signage)?
-
Public safety concerns are communicated to the OHSE Department?
Environmental
-
Excessively noisy tasks are not undertaken in the early morning? (Disturbing local community)
-
Vibration dampening equipment is installed where necessary?
-
Site fencing shade cloth is secured and in good condition to minimise dust movement?
-
Dust generated by vehicle movement is minimised?
-
Dust generated by concrete/brick cutting is minimised?
-
Water hoses turned off when not in use?
-
Water hoses/replaced when leaking?
-
Refuelling of plant is conducted at the designated area or by using appropriate size bund?
-
Designated concrete wash out is in use where practicable?
-
Site has been inspected for significant spills?
Audit Rating
-
RATING
-
ACTION REQUIRED
-
CORRECTIVE ACTION
Corrective Action
-
What?
-
By Who?
-
By When?
Worker Participation
- Worker Participation
-
Name:
-
Company Name:
-
Q1) Do you have any health and safety concerns that you would like to raise?
-
Q2) Is there anything within reason that Cooper & Oxley can do to make this site safer?
-
Q3) Do you have any general observations you would like to identify to Cooper & Oxley?