Audit

1. Engineer / Main Contractor approval of stressing records

Approved:

Approved by: DO NOT proceed until approval received

Select date
2. Preparation to grout

Cut strands for sufficient cover

External blocks pained with Sika Monotop 610

Stressing pockets sealed with dry pack mix
(ensure dry mix includes Masonry AU1)
20Kg dry sand cement to 100ml of Masonry AU1

Are all pockets sealed and tightly packed with dry mix

Check ducts are clear and have free passage of air

3. If ducts are not clear, report to leading hand, drill and clear

Are all ducts now clear?

How many needed to intermediate points added

Which tendons

Comments / Notes

Please add comments / notes as required

Main Contractor (Print Name and Sign)
Fortec Leading Hand (Print Name and Sign)
Please note that this checklist is a hypothetical example and provides basic information only. It is not intended to take the place of, among other things, workplace, health and safety advice; medical advice, diagnosis, or treatment; or other applicable laws. You should also seek your own professional advice to determine if the use of such checklist is permissible in your workplace or jurisdiction.