Information

  • Inspection Title. RMS Surveillance Checklist R11- Stormwater Drainage -Pipes ILC-MI-TP3-405-SC-R11-Pipes.

  • Project Name: Tabulam New Bridge.

  • Location: BRUXNER HIGHWAY TABULAM

  • Contractor

  • Prepared by

  • Conducted on

Work Activity Record

  • Cl 2.4.1

  • Has the hold point been released.

  • Cl 2.4.3 Are the precast pits manufactured specifically to suit the design.

  • Cl 2.4.4 Are the access covers and grates conforming. <br>Do grates include a fastening device which prevents their opening without the use of a tool.

  • Cl 2.4.5 Are ladders conforming.

  • Cl 2.5 Do the precast units have the correct markings on them.

  • Cl 2.6

    R11 HP 2.6
  • Cl 2.6 Has the Hold Point been released.

  • Cl 3.1.1 Does the type BH select fill for bedding and haunch zones have the following properties <br>(a) PI no greater than 6. <br>(b)PSD within the limits of Table 6 in AS 3725, (or Table 5.1 in AS. 1597.2) (see table section).

  • Cl 3.1.2 Does the type SO select fill for side and overlay zones have the following properties. <br>(a) Maximum particle size of 53mm.<br>(b) No more than 5% by mass passing the 9.5mm AS sieve.

  • Cl 3.2 Is the material placed adjacent to weep holes clean, graded, hard and durable crushed stone or river gravel, and have the following properties:<br>(a) maximum particle size of 53mm.<br>(b) No more than 5% by mass passing the 9.5mm sieve.

  • Cl 4.1.1

    Hp drainage set out
  • Cl 4.1.1 Has the Hold Point been released.

  • Cl 4.1.2 Have the required erosion and sediment control measures been implemented.

  • Cl 4.3

    R11 4.3 Witness Point.
  • Has the contractor notified of the Witness point.

  • Cl 4.3.1 Is the trench excavated to the widths shown on RMS model drawing MD.R11A01.B and AS 3725.

  • Cl 4.3.1 For pipes under embankment, where "Embankment Condition" installation is specified:<br>Construct the embankment to a height of at least .7 times the external diameter of the pipe above the top of bed zone. <br>Where "Trench Condition" installation is specified:<br>Construct the embankment to the underside of SMZ.

  • Cl 4.3.1 Has a alternative flow channel been provided where appropriate.

  • Cl 4.3.3 If inadequate foundation material is found:

    R11 C4.3.3 HP
  • Cl 4.3.3 Has the hold point been released by the Principal.

  • Cl 4.4.1 Is the correct pipe support type being used.

  • Cl 4.4.2 Are the pipes being handled and installed in accordance with the manufactures recommended practice.<br>Are the pipes being placed from the downstream end with the socket end upstream.

  • Cl 4.4.3 Have anchor blocks been installed at a maximum spacing of 3M and at bends or junctions for all pipes laid on a grade greater than 20% or where shown on drawings.

  • Cl 4.4.4 Have all lifting holes in the pipes, all flush holes or butt joints used to extend existing pipes been sealed.

  • Cl 4.4.5 Has a subsoil drainage pipe been installed at the discharge end of the pipes.

  • Cl 4.7.2 Have precast pits been installed on a minimum of 50mm thick DGB20 bedding material. <br>For drainage structures other than precast drainage pits been placed on a foundation of unreinforced concrete not less than 50mm thick.

  • Cl 4.7.2

    R11 WP 4.7.2
  • Cl 4.7.2 Has the contractor submitted the witness point.

  • Cl 4.7.3 Has a curtain wall been installed on the outer edge of the apron in accordance with RMS model drawings.

  • Cl 4.7.4 Do all pits which are deeper than 600mm have step irons installed.

  • Cl 4.9.1 Side and overlay zones to be backfilled with Type SO Select Fill.<br>Material to be compacted in 150mm compacted thickness.<br>Material to be compacted from structure out.

  • Cl 4.9.2 Compact the foundation and fill material to achieve the minimum CV as shown in Table R11.2

    Table R11.2
  • Cl 4.9.3 Have surplus material be disposed of in accordance with RMS R44.

  • Cl 4.10 Where you propose to move heavy construction plant and vehicles over pipe or box structures. Design and provide protective measures for each crossing.

    R11 4.10 HP
  • Cl 5.1 Has the stormwater drainage system been constructed so that water flows through the system without unintended ponding, and within the construction tolerances in Table R11.4 (see table section)

  • Cl 5.2 Has CCTV inspection of all pipe and box culvert with dimensions that restrict human access, to verify that the works have been constructed within the specified tolerances.:<br>(a) On completion of the subject drainage structure and prior to commencement of the overlying pavement <br>(b) No more than 14 days prior to completion.

G22 Safety and G36 Environmental

  • G22 SAFETY

  • Has a safe work and technical criteria been implemented for the connection of existing pipes to new pipes that have the same or grater size.

  • Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>

  • Has a SWMS been developed.

  • Is each and every item of plant being used for its designated and intended purposes.

  • Have the attachments for plant and processes been approved and used in accordance with their design and purposes.

  • Is the correct PPE being worn

  • Has a certified rigger checked that the structural members are secure before the load is released.

  • Have all slings been inspected and tagged.

  • Is the laser used approved for use.

  • Has a exclusion zone been established where a load is being lifted or suspended.

  • Is all lifting plant fitted with approved hooks/lugs and its SWL marked.

  • Was the item inspected for irregularities before being lifted.

  • Has safe entry/ exit been provided to excavations.

  • Has the excavation been battered/benched if depths greater than 1.5m, or if there is a possibility of collapse.

  • Has spoil been placed away from the excavation.

  • Were any unsafe practices observed. <br>

  • Good safe practices observed.

  • G36 ENVIRONMENTAL

  • R44 Cl 1.7 Were erosion and sediment controls in place prior to the removal of any topsoil.

  • Are Erosion and Sediment controls measures being installed prior to works commencing and are they being maintained.

  • Has mud been prevented from being deposited on roadways.

  • Have any environmental incidents or potential incidents been observed.

  • Good environmental procedures observed.

Compliance and Follow-up action.

  • Is the activity compliant.

  • Surveillance Officer

  • NCPN or memo number.

  • Follow up action

  • Product Non Conformance

  • System Non Conformance

  • Contractor generated NCR

  • Contractor generated a CAR

Matters arising

  • NCPN no

  • Contractors NCR no

  • CAR no

  • Closed out.

  • RMS representative's name

Tables

  • Table 6 AS 3725.

    Table 6
  • Cl 5.1 Table R11.4

    R11 table 11.4
  • Cl 5.1 Table R11.4 Part 2

    Table R.11.4 Part 2
The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.