Information
-
Inspection Title. RMS Surveillance Checklist R11- Stormwater Drainage -Pipes ILC-MI-TP3-405-SC-R11-Pipes.
-
Project Name: Tabulam New Bridge.
-
Location: BRUXNER HIGHWAY TABULAM
-
Contractor
-
Prepared by
-
Conducted on
Work Activity Record
-
Cl 2.4.1
-
Has the hold point been released.
-
Cl 2.4.3 Are the precast pits manufactured specifically to suit the design.
-
Cl 2.4.4 Are the access covers and grates conforming. <br>Do grates include a fastening device which prevents their opening without the use of a tool.
-
Cl 2.4.5 Are ladders conforming.
-
Cl 2.5 Do the precast units have the correct markings on them.
-
Cl 2.6
-
Cl 2.6 Has the Hold Point been released.
-
Cl 3.1.1 Does the type BH select fill for bedding and haunch zones have the following properties <br>(a) PI no greater than 6. <br>(b)PSD within the limits of Table 6 in AS 3725, (or Table 5.1 in AS. 1597.2) (see table section).
-
Cl 3.1.2 Does the type SO select fill for side and overlay zones have the following properties. <br>(a) Maximum particle size of 53mm.<br>(b) No more than 5% by mass passing the 9.5mm AS sieve.
-
Cl 3.2 Is the material placed adjacent to weep holes clean, graded, hard and durable crushed stone or river gravel, and have the following properties:<br>(a) maximum particle size of 53mm.<br>(b) No more than 5% by mass passing the 9.5mm sieve.
-
Cl 4.1.1
-
Cl 4.1.1 Has the Hold Point been released.
-
Cl 4.1.2 Have the required erosion and sediment control measures been implemented.
-
Cl 4.3
-
Has the contractor notified of the Witness point.
-
Cl 4.3.1 Is the trench excavated to the widths shown on RMS model drawing MD.R11A01.B and AS 3725.
-
Cl 4.3.1 For pipes under embankment, where "Embankment Condition" installation is specified:<br>Construct the embankment to a height of at least .7 times the external diameter of the pipe above the top of bed zone. <br>Where "Trench Condition" installation is specified:<br>Construct the embankment to the underside of SMZ.
-
Cl 4.3.1 Has a alternative flow channel been provided where appropriate.
-
Cl 4.3.3 If inadequate foundation material is found:
-
Cl 4.3.3 Has the hold point been released by the Principal.
-
Cl 4.4.1 Is the correct pipe support type being used.
-
Cl 4.4.2 Are the pipes being handled and installed in accordance with the manufactures recommended practice.<br>Are the pipes being placed from the downstream end with the socket end upstream.
-
Cl 4.4.3 Have anchor blocks been installed at a maximum spacing of 3M and at bends or junctions for all pipes laid on a grade greater than 20% or where shown on drawings.
-
Cl 4.4.4 Have all lifting holes in the pipes, all flush holes or butt joints used to extend existing pipes been sealed.
-
Cl 4.4.5 Has a subsoil drainage pipe been installed at the discharge end of the pipes.
-
Cl 4.7.2 Have precast pits been installed on a minimum of 50mm thick DGB20 bedding material. <br>For drainage structures other than precast drainage pits been placed on a foundation of unreinforced concrete not less than 50mm thick.
-
Cl 4.7.2
-
Cl 4.7.2 Has the contractor submitted the witness point.
-
Cl 4.7.3 Has a curtain wall been installed on the outer edge of the apron in accordance with RMS model drawings.
-
Cl 4.7.4 Do all pits which are deeper than 600mm have step irons installed.
-
Cl 4.9.1 Side and overlay zones to be backfilled with Type SO Select Fill.<br>Material to be compacted in 150mm compacted thickness.<br>Material to be compacted from structure out.
-
Cl 4.9.2 Compact the foundation and fill material to achieve the minimum CV as shown in Table R11.2
-
Cl 4.9.3 Have surplus material be disposed of in accordance with RMS R44.
-
Cl 4.10 Where you propose to move heavy construction plant and vehicles over pipe or box structures. Design and provide protective measures for each crossing.
-
Cl 5.1 Has the stormwater drainage system been constructed so that water flows through the system without unintended ponding, and within the construction tolerances in Table R11.4 (see table section)
-
Cl 5.2 Has CCTV inspection of all pipe and box culvert with dimensions that restrict human access, to verify that the works have been constructed within the specified tolerances.:<br>(a) On completion of the subject drainage structure and prior to commencement of the overlying pavement <br>(b) No more than 14 days prior to completion.
G22 Safety and G36 Environmental
-
G22 SAFETY
-
Has a safe work and technical criteria been implemented for the connection of existing pipes to new pipes that have the same or grater size.
-
Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor. <br>
-
Has a SWMS been developed.
-
Is each and every item of plant being used for its designated and intended purposes.
-
Have the attachments for plant and processes been approved and used in accordance with their design and purposes.
-
Is the correct PPE being worn
-
Has a certified rigger checked that the structural members are secure before the load is released.
-
Have all slings been inspected and tagged.
-
Is the laser used approved for use.
-
Has a exclusion zone been established where a load is being lifted or suspended.
-
Is all lifting plant fitted with approved hooks/lugs and its SWL marked.
-
Was the item inspected for irregularities before being lifted.
-
Has safe entry/ exit been provided to excavations.
-
Has the excavation been battered/benched if depths greater than 1.5m, or if there is a possibility of collapse.
-
Has spoil been placed away from the excavation.
-
Were any unsafe practices observed. <br>
-
Good safe practices observed.
-
G36 ENVIRONMENTAL
-
R44 Cl 1.7 Were erosion and sediment controls in place prior to the removal of any topsoil.
-
Are Erosion and Sediment controls measures being installed prior to works commencing and are they being maintained.
-
Has mud been prevented from being deposited on roadways.
-
Have any environmental incidents or potential incidents been observed.
-
Good environmental procedures observed.
Compliance and Follow-up action.
-
Is the activity compliant.
-
Surveillance Officer
-
NCPN or memo number.
-
Follow up action
-
Product Non Conformance
-
System Non Conformance
-
Contractor generated NCR
-
Contractor generated a CAR
Matters arising
-
NCPN no
-
Contractors NCR no
-
CAR no
-
Closed out.
-
RMS representative's name
Tables
-
Table 6 AS 3725.
-
Cl 5.1 Table R11.4
-
Cl 5.1 Table R11.4 Part 2