Information

  • Audit Title. R44 - Earthworks - Cuttings (Ed5 Rev 0) .

  • Project Name: Tabulam New Bridge.

  • Location: BRUXNER HIGHWAY TABULAM

  • Contractor

  • Prepared by

  • Conducted on

Work Activity Record

1 GENERAL

  • Cl 1.6.1 Has survey set out been installed for the cutting.

  • 1.7 PROTECTION OF EARTHWORKS

  • Provide and maintain measures for drainage of the working areas without scouring from the surface run-off. Do not allow water to pond in the working areas resulting in wetting up of the existing pavement or formation or foundation material, except where ponding is off the formation and forms part of a planned erosion and sedimentation control system.

  • When rain is likely, or when no work is planned for the following day in a particular area being worked, take precautions to minimise any ingress of water into the earthworks material. Seal off ripped material remaining in cuttings, and material placed on embankments, using a smooth drum roller.

  • Should earthworks material become over-wet (above the specified moisture content for compaction), replace and/or dry out the material at your own cost. Refer also to Clauses 2.4 and 7.2.

2 EARTHWORKS MATERIALS

  • Are erosion and sediment controls in place prior to commencing removal of topsoil?

  • Cl 2.3.3 HOLD POINT. Survey after removal of topsoil. Process Held: Any works which will alter the ground surface as surveyed.

  • Cl 2.3.3 HOLD POINT.

    no label
  • Has the hold point been released.

  • Cl 2.4 UNSUITABLE MATERIAL.

  • Cl 2.4 HOLD POINT.

    no label
  • Has the contractor notified that the unsuitable material has been removed as directed.<br>Has the Principal inspected the excavation and released the hold point.

  • Cl 2.7 BORROW AREAS

  • Has the selection and quality control of materials obtained from the borrow areas been detailed in the EARTHWORKS PLAN.

  • G1 Cl 42 HOLD POINT.

    no label
  • Has the principle released the Hold Point.

  • Is the Borrow pit being managed in accordance with the BPMP.

FOUNDATION TREATMENTS IN CUTTINGS.

  • Cl 3.4 HOLD POINT Process Held Treatment of each Lot of floor of cuttings.

  • Cl 3.4 HOLD POINT

    no label
  • Has the HOLD POINT been released.

  • What treatments have been ordered

  • Has the treatment been compacted to the required limits Table R44.10 CV 98%<br>Has the surface been trimmed to required tolerance Table R44.11 +0mm/+40mm

  • Cl 3.5.1 Has the shallow embankment been excavated to the depth stated in the annexure R44/A4.

  • Has the contractor proposed a lesser depth if so have they provided the CBR and PI results for the area.

  • Cl 3.5.2 Has the cut/fill transition been excavated as shown on the drawings or Figure (R44.6B)

4 CUTTINGS

  • Cl 4.1.2 have the material encountered in the cutting been loosened and processed as required.

  • Cl 4.1.3 Are the batters meeting the following requirements. <br>Batter slope as per drawings.<br>.<br>. <br>.

  • Cl 4.1.3 Free of Rills running down the slope.

  • Cl 4.1.3 Progressive flattening at the ends and tops rounded.

  • No undulations in the general plane.

  • Cl 4.3 Do batters comply with the tolerances given in table R44.3

  • Capture.PNG 27.PNG

G22 Safety and G38 Environmental

G22 SAFETY

  • Have operators demonstrated their competence to operate the plant/equipment to the satisfaction of the contractor.

  • Has a SWMS been developed.

  • Is each and every item of plant being used for its designated and intended purposes.

  • Have the attachments for plant and processes been approved and used in accordance with their design and purposes.

  • Is correct PPE being worn.

  • Were any unsafe practices observed.

  • safe work practices observed.

G36 ENVIRONMENTAL.

  • Are erosion and sediment control measures being installed and maintained.

  • Has mud been prevented from being deposited on roadways.

  • Have any environmental incidents or potential incidents been observed.

  • Good environmental practices been observed.

Compliance and Follow-up action.

  • Is the activity compliant.

  • NCPN or memo number.

  • Surveillance Officer

  • Follow up action

  • Product Non Conformance

  • System Non Conformance

  • Contractor generated NCR

  • Contractor generated a CAR

Matters arising

  • NCPN no

  • Contractors NCR no

  • CAR no

  • Closed out.

  • RMS representative's name

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.