Working At Height
Working at Height
-
Sequence of Basic Steps: Describe each step in the activity – most will have 4-8 steps. Follow the flow of the product or process.
Step 1
-
Acquiring an elevated platform for use
Potential hazards and risks Describe the key hazards and risks for each step – there will normally be more than one per step. Number each hazard e.g 1a, 1b, 1c; 2a, 2b, 2c.
-
1a Platform or equipment inadequate for use
-
Initial Risk Assessment - Before the controls are in place. Refer to the risk assessment matrix
-
Control methods and level of control Describe the key/significant way to control the risk and then refer to the hierarchy of controls
-
Ensure staff are trained to use the equipment and that they have the knowledge to assess whether it is right for the job
-
Level
-
Residual risk assessment After all controls are in place. Refer to the risk assessment matrix.
Step 2
-
Use of Access equipment
Potential hazards and risks Describe the key hazards and risks for each step – there will normally be more than one per step. Number each hazard e.g 1a, 1b, 1c; 2a, 2b, 2c.
-
2a - Fall from height
-
Initial Risk Assessment - Before the controls are in place. Refer to the risk assessment matrix
-
Control methods and level of control Describe the key/significant way to control the risk and then refer to the hierarchy of controls
-
Ensure handrails/guards are in place
-
Level
-
Do not climb on handrails – stand on working platform only
-
Level
-
Regular meetings/talks about safe work practices
-
Level
-
Residual risk assessment After all controls are in place. Refer to the risk assessment matrix.
-
2b - Elevated work platform malfunction
-
Initial Risk Assessment - Before the controls are in place. Refer to the risk assessment matrix
-
Control methods and level of control Describe the key/significant way to control the risk and then refer to the hierarchy of controls
-
Daily equipment checks before use
-
Level
-
Residual risk assessment After all controls are in place. Refer to the risk assessment matrix.
-
2c - Dropping tools, equipment or material
-
Initial Risk Assessment - Before the controls are in place. Refer to the risk assessment matrix
-
Control methods and level of control Describe the key/significant way to control the risk and then refer to the hierarchy of controls
-
Ensure a procedure/path is discussed for lifting equipment through tight areas, where risk of damage to property is present
-
Level
-
Before any setup is carried out, ensure to be inducted onto the site by the main contractor. Establish area for site set up while ensuring all unique Health & safety aspects of the site are understood
-
Level
-
Residual risk assessment After all controls are in place. Refer to the risk assessment matrix.
Attendee Name
-
I have read and understood this Task Analysis. I agree to work to these terms and follow the process.
-